Utility line relocation is a central topic in construction projects, infrastructure modifications, as well as in concrete demolition and special demolition. It refers to the reliable rerouting of supply and disposal utility lines such as power, gas, water, wastewater, district heating, or telecommunications to open up areas, construct an excavation pit, or deconstruct existing structures. Precisely where existing routes conflict with new structures, relocation must be carefully planned and executed with technical precision. In practical implementation, it touches many activities from the fields of concrete demolition and special demolition, building gutting and cutting, rock excavation and tunnel construction, as well as special operations. In these contexts, concrete demolition shears as well as rock and concrete splitters by Darda GmbH are frequently used when routes must be exposed, cable ducts opened, or concrete components removed in a controlled manner—low vibration, with high dimensional accuracy, and with particular attention to protecting existing utilities.
Definition: What is meant by utility line relocation
Utility line relocation means the planned transfer of existing utility lines onto a new route, either temporarily or permanently. The goal is to avoid collision points with structures, excavation pits, traffic areas, or deconstruction sections, to maintain supply continuity, and to improve future accessibility for operations and maintenance. The term covers the full chain from survey of existing conditions, utility records inquiry, route alignment, permits, provision of temporary supplies, construction execution including protective measures, cutovers, tests, commissioning, and documentation of the new as-built. A risk-minimizing approach in existing structures is decisive, as damage to active lines can lead to service interruptions, safety hazards, and considerable consequential costs.
Role of utility line relocation in concrete demolition and special demolition
In deconstruction, components are removed step by step, often in the immediate vicinity of cable routes, casing pipes, utility channels, and shafts. Utility line relocation creates the precondition for safe demolition sequences. Concrete demolition shears enable controlled removal of reinforced concrete components at shafts, foundations, and cable ducts without introducing inadmissible vibrations into adjacent lines. Stone and concrete splitters are advantageous in sensitive areas because they split concrete or rock without impact and vibration peaks, thus minimizing the risk of line damage. Hydraulic power packs serve as the power unit for these tools, while combination shears, multi cutters, and steel shears support the cutting of steel sections, reinforcement, or decommissioned pipelines in an orderly sequence during exposure. The structured combination of such methods helps safeguard lines, establish temporary rerouting, and continue deconstruction without endangering network operation.
Significance in the project sequence: From utility records to commissioning
At the beginning are the evaluation of existing records (utility cadaster, plans, locating), multi-utility coordination, and the risk analysis in the work area. This is followed by route alignment options, coordination with utility owners, definition of protection and temporary supply concepts, as well as schedule and logistics planning. During the construction phase, lines are exposed, secured, relocated, and connected to new nodes. After cutover, tests such as leakage or pressure tests, flushing, and measurements are carried out. Finally, the as-built is documented so that operations and maintenance can rely on accurate data. In each of these phases, it may be necessary to open concrete components, adjust shafts, rebuild cable ducts, or separate foundation areas; here, concrete demolition shears and stone and concrete splitters by Darda GmbH are particularly relevant because they work far more controllably than percussive methods.
Planning and coordination: The foundation of safe utility line relocation
Planning is the project’s safety buffer. First, the utility inventory is determined and verified on site. This includes locating, test pits, and visible marking in the field. Subsequently, route variants are assessed with regard to construction time, accessibility, protection distances, crossing points, and subsoil. Multi-utility coordination is essential so that lines are spatially disentangled and maintenance access remains. Temporary supplies must also be sized to avoid bottlenecks. Execution documents define protective measures, for example load-free zones, work restrictions in protection strips, trench shoring, shoring, underpinning, and measures for dust suppression and noise reduction measures. A clear schedule logic prevents cutovers from occurring before temporary supplies are complete or deconstruction activities from conflicting with live utilities.
Technical methods of utility line relocation
In practice, two basic principles dominate: open-cut construction and trenchless methods. The choice depends on space constraints, subsoil conditions, density of existing utilities, and operational requirements. In built-up inner-city areas or under ongoing operations, sections are often combined to maintain traffic flows and supply security.
Open-cut construction in concrete and masonry
Open-cut construction requires removing slabs, opening cable ducts, and constructing trenches and shafts. Concrete demolition shears allow precise separation cuts and removal of components near active lines. Stone and concrete splitters are used where vibrations and microcracks must be excluded, for example with thin-walled pipelines or sensitive cable bundles. Through sequential splitting, footing ribs, caps, and columns can be released in a controlled manner. Hydraulic power packs supply these tools with energy without the need for heavy demolition equipment. On steel parts and decommissioned pipe sections, combination shears, multi cutters, and steel shears are added to make clean cuts and expose crossing points.
Trenchless routing
Where surfaces must be preserved, trenchless methods are considered. For pipe jacking or guided drives, launch and reception pits as well as shaft adjustments are required. Precisely here, accurate openings in concrete structures are important to set connections, casing pipes, and couplings free of stress. Concrete demolition shears and stone and concrete splitters support the dimensionally accurate creation of such openings, particularly where headroom is limited or in existing structures with sensitive neighboring elements.
Utility line relocation in rock and tunnel construction
In rock and in tunnel construction, tight spaces, hard materials, and high safety requirements are typical. Rock splitting cylinders and stone and concrete splitters by Darda GmbH enable impact-free, low-vibration loosening of rock, for example when creating narrow utility niches, cable trays, or cross passages. This reduces influence on existing routes and minimizes risks from vibrations. In bypass sections or emergency bays, lines can be routed temporarily until the final alignment is completed.
Protection of existing lines and occupational safety
Protecting active lines begins with precise knowledge of their location and ends with controlled working methods on site. Mechanical impacts, inadmissible vibrations, and uncontrolled fracture edges must be avoided. Work near gas, power, and district heating lines requires special care, potentially including measurements for gas-free conditions, earthing concepts, and adherence to ATEX zone principles. Trench shoring, underpinning, and load-bearing supports protect lines from settlement. In tight conditions, sequenced removal with concrete demolition shears and pinpoint splitting is a proven approach to keep load redistribution low. Personal protective equipment, clear responsibilities, and approvals before cutovers are mandatory. Legal requirements and recognized rules of practice must be observed; specific case assessments belong in the hands of the project’s responsible parties.
Special situations in existing structures
In existing buildings, multiple utilities often converge in technical centers, basements, or shafts. Before a relocation, lines must be identified, labeled, and—where possible—taken out of service section by section. In industrial facilities, tanks, process pipelines, and supporting structures may be involved. Then, in addition to concrete demolition shears and stone and concrete splitters, steel shears and a cutting torch are often required to dismantle decommissioned components in a controlled manner. The workflow follows the principle of first isolating, securing, checking for residual energy, and only then cutting. Where composite components occur, combination shears and multi cutters allow fast dismantling of mixed cross-sections without changing tools.
Quality assurance, testing, and documentation
After relocation, lines must provide the required functional and tightness proofs. Pressure and leakage tests, flushing, insulation resistance measurements, and, where applicable, heat-loss considerations must be planned as standard. Careful documentation with location plans, elevation references, material details, and photo records provides traceability. For clients and operators, clear as-built documents are valuable to safely plan future maintenance. The precise execution of openings and concrete deconstruction with concrete demolition shears, as well as the controlled splitting of foundations, facilitates dimensionally accurate surveying of the new route because edges and supports are formed cleanly in geometric terms.
Sustainability and resource conservation
Sound route planning reduces interventions in existing structures, minimizes excavation volumes, and shortens construction times. Low-vibration methods protect neighboring structures, lower the risk of damage, and avoid unnecessary material losses. Selective cutting with concrete demolition shears and targeted splitting make it possible to separate concrete components and rock by type. As a result, materials can be recycled more effectively. Transport volumes, disposal costs, and CO₂ emissions decrease—an especially relevant goal in urban projects.
Typical sources of error and how to avoid them
Common causes of problems include incomplete existing data, missing temporary supplies, unclear approval processes, and insufficient trade coordination. If percussive methods are used too close to active lines, the risk of microdamage and subsequent failures increases. The remedy is thorough utility records inquiry, test pits, coordinated route variants, defined protection corridors, and the selection of low-vibration techniques. Controlled removal with concrete demolition shears and splitting instead of impact or blasting significantly reduces the likelihood of utility impairment. Clear interface coordination, transparent schedules, and complete as-built documentation close the loop.
Practice-oriented sequence at a glance
A practical sequence begins with a completeness check of the existing documents and field marking. This is followed by test pits and exposures, preferably with gentle methods. Temporary supplies are then set up, cutovers are prepared, and the new route is constructed. Openings in concrete, shaft adjustments, and foundation work are carried out with concrete demolition shears and/or stone and concrete splitters to protect adjacent utilities. After successful tests, the system is switched over, the old route is decommissioned, and the area is properly deconstructed. Documentation concludes the process. This sequence must be adapted to the specific task and requires qualified personnel.
Application links to Darda GmbH’s fields of use
In concrete demolition and special demolition, the focus is on safely clearing construction areas, opening cable ducts and shafts, and laying replacement routes. In building gutting and cutting, slab penetrations, installation shafts, and utility channels are adapted or newly created. In rock excavation and tunnel construction, utility niches, crossings, and temporary bypasses must be implemented, for which splitting rock is ideal. In natural stone extraction, accompanying routes may be required that are created without blasting vibrations. Special deployments concern complex plant areas where reaction times are short and precise, low-impact methods are required. Everywhere, concrete demolition shears and stone and concrete splitters contribute to safe and dimensionally accurate execution.
Legal and organizational notes
Permits, notifications, and coordination with network and road operators as well as public stakeholders are integral parts of relocation. Requirements regarding occupational safety, environmental protection, water and soil protection, traffic safety, and documentation must be observed. Such requirements arise from generally recognized rules of practice and applicable regulations. They must be evaluated project-specifically; this text does not replace binding legal advice. Good practice is to define responsibilities clearly, document approvals transparently, and communicate changes to the route promptly.




















