Felling cut

The term felling cut originates from forestry and describes the targeted creation of cuts to safely control the fall direction of a tree. In deconstruction and dismantling of structures, this principle is analogously used to deliberately tip components such as columns, wall segments, chimneys, or free-standing concrete bodies in a controlled manner. The felling cut combines pre-weakening (pre- or relief cuts) with a remaining hinge zone and the final separation cut. For concrete demolition and special demolition, building gutting and concrete cutting, as well as special operations, the concept is relevant because it directs the movement and energy input. For context, see concrete demolition and deconstruction. In projects where equipment from Darda GmbH is used, the basic idea is often implemented with concrete pulverizers and hydraulic splitters, such as hydraulic rock and concrete splitters, to create predetermined breaking lines, form cavities, and guide removal in a controlled way.

Definition: What Is Meant by a Felling Cut

A felling cut is understood to be the combination of a targeted pre-opening (comparable to the felling notch) and a rear separation cut that together form a hinge zone. This zone holds the component up to a defined tipping moment and guides the fall direction. Transferred to deconstruction, this means: components are weakened so that they tip in a planned direction under controlled conditions, while the remaining cross-sections, reinforcement, or remaining material bridges guide the movement until the separation cut or a defined failure causes complete detachment. In concrete and masonry, pre-weakening is often carried out by saw cuts, core drilling, local material removal, or hydraulic splitting; the final intervention can be performed with concrete pulverizers or hydraulic splitters.

Application to Concrete Demolition: Principles and Specifics

Unlike wood, concrete is heterogeneous and often interlaced with reinforcement. This requires precise planning of cut geometries and residual cross-sections. The goal remains to form a guiding kerf and a load-transferring hinge up to the tipping point. Saw cuts, relief openings, and hydraulically induced crack lines create a defined weakening. Concrete pulverizers then attack the remaining webs, open the separation cut, and control step-by-step removal. Hydraulic splitters are particularly suitable for creating predetermined breaking points without vibrations and steering the fracture behavior toward the desired tipping line.

Tools and Equipment in the Context of the Felling Cut

The choice of equipment depends on component geometry, material, reinforcement ratio, and environmental conditions. In connection with the felling cut, the following Darda GmbH devices are frequently integrated:

  • Concrete pulverizers: Localized removal, opening remaining webs, reworking the hinge, controlled laying down of component heads.
  • Hydraulic splitters as well as rock wedge splitter: Creating predetermined breaking lines in massive cross-sections; low-vibration and precise.
  • Hydraulic power packs: Power supply for hydraulic attachments and handheld tools; crucial for timing and force control.
  • Hydraulic demolition shears and Multi Cutters: Cutting mixed cross-sections where concrete, masonry, and light steel components meet.
  • Steel shears: Severing reinforcement, profiles, or anchoring structures when the hinge zone needs to be selectively exposed.
  • Tank cutters: Special operations on thin-walled vessels and pipelines when components are laid down in a controlled manner similar to a felling cut.

Areas of Application and Typical Components

The principle of the felling cut is used in different applications when components are to tip or be laid down in a planned direction:

  • Concrete demolition and special demolition: Free-standing concrete columns, edge piers, wall slabs, stair landings.
  • Building gutting and concrete cutting: Opening and notching wall segments for subsequent dismantling.
  • Rock excavation and tunnel construction: Beveling rock ribs and releasing blocks along defined separation joints.
  • Natural stone extraction: Detaching larger stone packages along splitting joints for controlled stockpiling.
  • Special demolition: Laying down chimneys, masts, or vessels under confined space conditions.

Concrete Columns and Piers

For slender columns, the felling cut enables a plannable tipping motion. Relief cuts and hydraulic splitters create the fracture line; concrete pulverizers release remaining webs until the element tips in a guided manner.

Wall Slabs and Wall Segments

Horizontal and vertical saw cuts form the hinge zone. Opening the separation cut with concrete pulverizers reduces uncontrolled spalling.

Chimneys and Masts

Analogous to the tree-typical felling notch, an opening is created in the fall direction; on the rear side, a separation cut or hydraulic splitting leads to the controlled tipping motion.

Rock Blocks and Natural Stone

Splitting boreholes define the fracture surface; rock wedge splitter drives the crack. The component tips along the desired line.

Process in Practice: From Planning to Implementation

The specific process depends on structural analysis, building condition, and surroundings. Typical steps are:

  1. Determine fall direction, tipping axis, and required exclusion zones; define the hinge zone.
  2. Specify the cut geometry (depth, height, angle) and the remaining cross-sections.
  3. Create the pre-opening by sawing, drilling, or hydraulic splitters.
  4. Expose and, if necessary, cut reinforcement with steel shears or hydraulic demolition shears.
  5. Controlled opening of the separation cut with concrete pulverizers; accompany the tipping motion with safeguards.
  6. Rework the fracture edge, remove remnants, and create clean termination faces.

Important: The sequence and tools must be selected specific to the object; load redistribution during opening must be continuously monitored.

Safety and Legal Notes

Work with the felling cut requires a coordinated safety concept. Barriers and tipping/hazard zones must be generously dimensioned. Depending on the situation, auxiliary safeguards (tag lines, pulling devices, shoring props) can be useful. Legal and regulatory requirements vary by location and measure; they should be reviewed in advance and coordinated with occupational safety and health protection. The notes in this text are general in nature and do not replace object-specific planning.

Quality Characteristics and Control

  • Defined fall direction and reproducible tipping moment.
  • Clean hinge zone without uncontrolled crack formation.
  • Low vibrations and a controlled fracture pattern.
  • Minimized secondary damage to adjacent components.
  • Documented cut geometry, forces, and tools used.

Typical Error Patterns and How to Avoid Them

  • Oversized remaining webs: Tipping process fails to occur or is jerky. Remedy: precise sizing, incremental opening with concrete pulverizers.
  • Undersized hinge zone: Premature failure, uncontrolled fall motion. Remedy: conservative remaining cross-sections and continuous control.
  • Ignored reinforcement: Unexpected force redirections. Remedy: investigate reinforcement routing, sever where necessary with steel shears.
  • Missing relief: Crushing and spalling damage. Remedy: pre-weakening with hydraulic splitters or drilling/saw cuts.

Delimitation and Alternative Approaches

Not every component is laid down using a felling cut. Section-by-section removal is often more appropriate, such as successive nibbling with concrete pulverizers or producing smaller blocks with hydraulic splitters. Alternatives include lifting and crane methods with prior complete separation, or pure sawing without a tipping motion. The selection criterion is always the environment, permissible vibrations, and the required protection of adjacent structures.

Planning Notes for Use in the Urban Environment

In existing inner-city settings, noise, dust, and vibrations must be particularly limited. Hydraulic methods with hydraulic splitters are suitable for this, as they enable controlled crack formation with low vibration levels. Concrete pulverizers allow material-conserving reworking with good control of fracture edges, which facilitates subsequent steps such as surveying or producing connection details.

Role of Selected Darda GmbH Devices in the Felling Cut

In the course of a felling cut, devices from Darda GmbH assume complementary tasks: hydraulic splitters create defined predetermined breaking points in massive cross-sections; concrete pulverizers open and guide the separation cut and reduce remaining cross-sections in a metered way; steel shears sever reinforcement where it would otherwise unacceptably impede the tipping motion. Hydraulic power packs provide the necessary power in a controlled manner so that the steps can be executed precisely in sequence. This combination supports a controlled tipping motion while simultaneously reducing environmental impacts.

Material- and Structural-Related Aspects

Concrete strength, cross-section thickness, reinforcement ratio, and bond condition influence tipping behavior. Higher strengths and dense reinforcement generally require deeper pre-openings and higher splitting forces. Masonry exhibits more brittle behavior; here, rock wedge splitter provide a good way to selectively activate joints and bed joints. In natural stone, the course of discontinuities determines the location of the hinge zone; hydraulic splitting exploits these weaknesses to stabilize the felling cut along the desired line.

Post-Processing and Surfaces

After tipping, fracture surfaces are often irregular. Concrete pulverizers are used to dress edges, remove loose parts, and produce defined termination lines. Where subsequent trades require precise connection dimensions, the surface is additionally sawn or leveled. The combination of hydraulic splitting and targeted reworking keeps material removal low and supports an orderly project flow.