The cost-effectiveness analysis in construction determines which work method, equipment combination, and sequence on the construction site is technically appropriate and at the same time cost-efficient. Especially in areas such as concrete demolition and special demolition, interior demolition and cutting, rock excavation and tunnel construction, natural stone extraction, as well as special operations, costs, performance, risks, and constraints must be evaluated precisely. In deconstruction, particular focus often lies on methods using concrete pulverizer as well as concrete splitter and rock wedge splitters, which, due to low vibration levels, selective operation, and plannable cycle times, often require their own calculation logic. This article links the fundamentals of investment appraisal with proven practical key figures for equipment such as hydraulic power pack, hydraulic demolition shear, Multi Cutters, steel shear, cutting torch, rock wedge splitter, and concrete pulverizer—objective, well-founded, and without promotional exaggeration.
Definition: What is meant by cost-effectiveness analysis in construction
Cost-effectiveness analysis in construction is the systematic analysis and comparison of alternative courses of action on a construction site over the entire relevant period. The goal is to minimize total costs while complying with all technical, scheduling, safety-related, and regulatory requirements. Typical methods include cost comparison, net present value and annuity methods, as well as life-cycle cost considerations (Total Cost of Ownership). In the context of demolition, deconstruction, and extraction, in addition to equipment costs and personnel, cycle times, performance metrics, setup effort, disposal and recycling revenues, emissions (noise, dust, vibrations), and permit requirements must be considered. For a valid decision, alternatives such as the use of a concrete pulverizer, concrete splitter, hydraulic demolition shear, or other hydraulic cutting and separation tools are quantitatively compared.
Methodological fundamentals of cost-effectiveness in construction
A robust calculation follows a clear sequence: define objectives, collect boundary conditions, define alternatives, determine quantities and outputs, assign cost types, structure cash flows over time, account for risks, and finally select the best option. The price basis (index level, cut-off date), the duration, and the discount rate should be chosen consistently. A two-step approach has proven itself in practice: first a robust cost comparison on an hourly, daily, or quantity basis; then—if durations are longer or investments are involved—the net present value assessment.
Cost comparison and net present value
The cost comparison method contrasts the sum of fixed and variable costs of the alternatives. Net present value discounts future cash flows to the price basis and includes investments, residual values, and possible revenues (e.g., scrap). For short-term deconstruction measures with rental or internal hourly rates, cost comparison is often sufficient. For the purchase and long-term use of a concrete pulverizer, rock wedge splitter, or a hydraulic power pack, the net present value calculation provides additional insights.
Fixed and variable costs
Fixed costs: equipment standby, depreciation or rental lump sums, transport, setup times, base allowances for the hydraulic power pack. Variable costs: productive machine hours, personnel, energy (diesel, electricity), wear parts (jaws, cutters, wedges, drill bits), disposal per tonne, specific add-on services (core drilling, saw cut, rebar cutting).
Price basis, indexation, uncertainties
Relate all prices to a cut-off date and escalate for longer durations with an appropriate index or markup. Uncertainties are shown as risk/opportunity ranges or assessed via sensitivity analyses (e.g., +/- 15% productivity, +/- 10% disposal price).
Performance metrics and equipment configuration in concrete demolition
Performance metrics are the basis of every quantity and time determination. In hydraulic cutting and splitting methods, productivity depends on component dimensions, reinforcement content, accessibility, carrier machine, tool geometry, and the performance of the hydraulic power pack.
Concrete pulverizer: selective deconstruction with predictable cycles
A concrete pulverizer crushes concrete and cuts reinforcement, often with lower vibrations than breaker hammer tools. The cycle time consists of positioning, applying, closing (crushing), opening, and relocating. Influencing factors are jaw opening, closing speed, cutting and crushing force, component thickness, and reinforcement density. In the calculation, cycles per hour, average fragment size (impact on haulage logistics), and the share of rework (e.g., separately cutting heavier reinforcement with a steel shear) are considered. For sensitive environments, lower noise emission and vibrations and longer allowable working hours have a positive impact.
Concrete splitter and stone splitting devices: controlled splitting instead of hammering
Stone and concrete splitters, such as hydraulic rock and concrete splitters, work on a wedge- or cylinder-based principle. The main driver of performance is drilling time (hole diameter, spacing, depth), followed by insertion, pre-tensioning, and the splitting process. Relevant are the required hole geometry, available splitting force, the maximum permissible system pressure, and the cycle time of the hydraulic power pack. Advantages include low vibrations, reduced dust exposure, and high dimensional accuracy, which often proves economical for tunnel connections, building extensions, or natural stone extraction—especially where blasting replacement or vibration limits are required.
Hydraulic power pack: energy demand, sizing, and operating time
Hydraulic power packs (see Hydraulic power units) provide flow and pressure for the concrete pulverizer, hydraulic demolition shear, Multi Cutters, steel shear, cutting torch, and splitters. The calculation includes full-load hours, part-load factors, fuel or electricity consumption per hour, maintenance intervals, and any emission requirements. Correct sizing avoids bottlenecks (too little flow prolongs cycle times) and oversizing (unnecessary cost per operating hour).
Cost types, influencing factors, and key figures
A clean cost structure improves comparability and post-calculation. The following items are typical:
- Direct equipment costs: rental or imputed equipment costs per hour, consumption, wear parts (pulverizer jaws, wedges, drill bits).
- Personnel: operator, drilling crew, signaler, support for material sorting.
- Setup and logistics costs: transport, assembly and disassembly, travel to/from site, site setup.
- Disposal and recovery: concrete, mixed demolition waste, reinforcing steel (with potential revenues), hazardous substances.
- Site operations: energy, operating supplies, maintenance operations, standby times, weather effects.
- Constraints: working hour windows, noise control and vibration limits, dust protection, difficulties (height, tight spaces, safety measures).
- Risk allowances: geometry deviations, unexpected reinforcement, interruptions, rework.
Disposal, separation, and revenues
Selective deconstruction with a concrete pulverizer facilitates separation of concrete and steel. Higher purity can reduce disposal costs and increase steel scrap revenues. Splitting methods often produce coarser material that can be secondarily crushed to defined grain sizes. Costs for secondary crushing and transport must be considered depending on quantity and fragment size.
Emissions and neighborhood impact
Methods with low vibrations and moderate noise emission can allow longer daily working hours. This reduces fixed costs per section. At the same time, dust- and vibration-reduced methods minimize additional efforts for protective enclosure, monitoring system, and complaints management.
Step-by-step calculation: practical example
As an example, consider the deconstruction of a 60 cm thick, reinforced concrete element in an inner-city environment. Two alternatives are compared: A) concrete pulverizer; B) concrete splitter with pre-drilling.
1. Record input data
- Quantities: volume (m³), steel content (kg/m³), cut lengths.
- Geometry: component thickness, access, obstacles, safety distance.
- Constraints: working hours, emission limits, load-bearing capacity of setup areas.
- Equipment: pulverizer jaw opening, cutting/crushing force; splitter force, wedge geometry; hydraulic power pack (operating pressure/flow).
- Logistics: transport routes, loading times, container changeovers, disposal routes.
- Prices: hourly rates, disposal €/t, scrap revenue €/t, energy €/l or €/kWh.
2. Set performance values
- Alternative A (concrete pulverizer): cycles per hour, average removal rate (m³/h), share of rebar rework (%), downtime and relocation times.
- Alternative B (splitting): drilling rate (m/h), number and grid of boreholes, splitting cycles per hour, secondary breaking and handling.
- Hydraulic power pack: load factor, specific consumption, maintenance share per operating hour.
3. Time and cost calculation
- Productive hours = quantity / performance value (m³/h).
- Equipment costs = productive hours × hourly rate (incl. wear, energy).
- Personnel = (operator + helpers) × hours × labor rate.
- Setup/transport = lump sums + time allowances × rates.
- Disposal = mass (t) × disposal price – scrap revenue.
- Constraints = additional efforts for protection, measurements, containment.
- Contingency/risk = percentage markup on variable costs.
4. Assessment and decision
The total costs are compared methodically. In addition, schedule (calendar duration), emission targets, quality requirements, and sensitivities (e.g., drilling rate +/- 20%) are considered. In inner-city projects, lower vibrations of the concrete pulverizer or the high dimensional accuracy of splitting can improve overall cost-effectiveness despite different base hourly rates.
Application areas in cost comparison
Concrete demolition and special demolition
A concrete pulverizer shows advantages in selective deconstruction, knotty reinforcement, and limited work windows. The calculatory strength lies in predictable cycles and reduced rework on protection measures. Splitters help with particularly sensitive components where vibration limits are strict or adjacent structures must be preserved. For method boundaries and typical constraints, see concrete demolition and special deconstruction.
Interior demolition and cutting
Interior demolition requires precise separation cuts and controlled dismantling. Hydraulic demolition shear, Multi Cutters, and steel shear complement the concrete pulverizer when pipes, profiles, and reinforcement must be systematically separated. Economically relevant are short setup times, clean material separation, and low spark or heat input. A cutting torch is considered for special steel tanks and thick walls, with protection and clearance costs properly allowed for.
Rock excavation and tunnel construction
Concrete splitter and rock wedge splitter are used as blasting replacement or to optimize advance rates. Drilling rate largely determines the cycle time. Advantages arise from reduced support effort, low vibrations, and precise fracture edges, which minimize rework.
Natural stone extraction
In extraction, dimensional accuracy of blocks is crucial. Splitters deliver smooth separation faces and reduced waste. The calculation considers the ratio of drilling time, splitting time, output (m³ of block material), and the value of the recovered quality.
Special operations
For special tasks such as opening thick foundation bodies, controlled separation of extensions, or deconstruction in vibration-sensitive areas, calculations often combine a concrete pulverizer with splitters. Strengths are leveraged to minimize setup and downtime while reliably meeting permit requirements.
Factors influencing cost-effectiveness
- Component properties: thickness, reinforcement content, accessibility, material quality.
- Equipment parameters: jaw opening and force of the concrete pulverizer, splitting force and wedge geometry, performance data of the hydraulic power pack.
- Logistics: travel distances, crane accessibility, container turnover, loading times.
- Constraints: working hours, emission limits, weather, safety.
- Team organization: interfaces between drilling, splitting/pulverizer work, loading, and haulage logistics.
Sensitivity analysis and scenarios
It is sensible to vary central drivers:
- Performance +/- 15% (cycles/h, drilled meters/h).
- Disposal price +/- 20% and scrap revenue +/- 15%.
- Energy price (diesel/electricity) +/- 25%.
- Working hour windows (extension/reduction) and their effect on fixed costs.
The most economical alternative is often the one with the least dispersion of critical parameters and the highest schedule reliability—especially in inner-city projects.
Data basis, documentation, and post-calculation
Good data enables good decisions. Cycle times (opening/closing/relocating), drilling performance, wear-part consumption, and reasons for downtime should be recorded continuously. A structured post-calculation compares planned and actual values, improves the key-figure library, and sharpens selection criteria for a concrete pulverizer, concrete splitter, hydraulic power pack, and complementary tools.
Legal and normative framework
Permits, occupational safety, and environmental protection measure requirements influence the choice of method. In general: emission limits, neighborhood protection, hazardous substance issues, and requirements for construction waste separation should be included in the calculation at an early stage. The specific interpretation is project-specific based on the applicable rules and requirements.
Avoiding typical calculation errors
- Underestimation of setup, waiting, and relocation times.
- Insufficient consideration of reinforcement content and its impact on cycle times.
- Lack of alignment between hydraulic power pack performance and tool demand.
- Allowances that are too tight for disposal and rework (secondary crushing, separation, sorting applications).
- Neglect of emission requirements and their cost consequences.
- No sensitivity analysis for the most important drivers.
Selection criteria for equipment and methods
Equipment selection follows the interplay of component, target condition, and constraints:
- Concrete pulverizer: selective deconstruction, controlled fragmentation, low vibration, steel separation possible.
- Concrete splitter: precise, low-vibration separation, high dimensional accuracy; note drilling dependency.
- Hydraulic demolition shear, Multi Cutters, steel shear: material-specific cutting performance on steel and composite parts.
- Cutting torch: special cutting for massive steel bodies with safety measures.
- Hydraulic power pack: tailored sizing for operating pressure/flow, efficient and reliable in cycle.
Checklist for bidding and execution phases
Bidding phase
- Complete quantity takeoff (m³, t, lf) and reinforcement assumptions.
- Equipment/tool configuration per alternative (incl. hydraulic power pack).
- Performance values with sources/experience and sensitivity.
- Disposal, recycling, transport chains, and time windows.
- Setup concept, access, load-bearing capacity, safety concept.
- Cost structure incl. risk/opportunity ranges.
Execution phase
- Daily reports with cycles, drilled meters, downtime, and consumption.
- Ongoing adjustment of cycle timing (crew, logistics, tool changes).
- Quality control of fragment sizes and separation purity.
- Compliance with emission requirements, documentation, and evidence.
- Post-calculation to improve future projects.




















