Pipe insertion is a trenchless construction method used in underground pipeline construction. It is employed to install sewer lines, siphons (dukers), cable protection conduits, or transmission pipelines beneath roads, railways, rivers, and built-up areas without extensive surface opening. Constructing start and reception shafts, jacking pipes, and safely passing through different ground types require precise planning, robust technology, and skilled execution. In the shafts, as well as during launch and retrieval of the drive, work on concrete and rock is frequently required. In practice, tools from Darda GmbH such as concrete pulverizers and hydraulic rock and concrete splitters are used here, for example when adjusting openings, performing controlled deconstruction, or during special operations in rock.
Definition: What is meant by pipe insertion
Pipe insertion refers to introducing pipes into the ground by pressing from the start shaft toward the reception shaft. A tunneling machine or shield cuts the ground at the face and removes the material via conveying equipment. The pipes are pushed forward behind the machine in increments using jacks. Guidance, surveying, and lubrication (for example with bentonite) ensure the alignment and grade are achieved correctly. Depending on the machine technology, pipe diameter, and ground conditions, the method is often referred to as microtunneling, pipe jacking, or press boring.
Construction methods and variants in pipe insertion
The choice of method depends on diameter, length, ground, groundwater, and permissible settlements. It is crucial to coordinate the tunneling machine, the mucking concept, and the reaction/lodging of jacking forces.
Microtunneling with a closed face
For dense soils, in groundwater, and over long distances, a closed-face machine is used, for example as a slurry or earth pressure system. The face is actively supported, and the spoil is removed hydraulically or mechanically. Typical diameters range from DN 200 to DN 3000. Intermediate jacking stations reduce friction loads over long drives.
Pilot pipe jacking and guidance
For high installation accuracy, for example with gravity pipelines, a pilot pipe jacking method with a steerable head and laser/gyro reference is used. The pilot is followed by a reaming and product pipe sequence. The guidance allows tight tolerances in position and elevation.
Open face and press boring
In stable soils or rock, open-face operation is possible, sometimes with drilling/milling tools at the face. Material transport takes place via augers or chain conveyors. When encountering obstacles, controlled pre-measures are required. In shafts, rock and concrete splitters are often used for this purpose to achieve local adjustments without vibrations.
Start and reception shafts: construction, outfitting, and deconstruction
Shafts accommodate the jacks, guide structures, and surveying equipment. Depending on boundary conditions, they are constructed in cast-in-place concrete, as precast shafts, or as sheet pile cofferdams. Space, bracing, groundwater control, and the connection to existing networks are decisive. During breakthrough (launch or retrieval), openings in concrete structures must be created or adapted.
- Concrete pulverizers are used to cut and break openings, windows, and edges in a controlled, low-vibration manner, for example for breakthrough into existing structures or for dismantling temporary components.
- Rock and concrete splitters enable the opening of massive cross-sections or the loosening of competent rock in the shaft area without blasting and with reduced noise emission.
- Hydraulic power units supply these tools safely and reliably in the shaft; hose routing and supports must be coordinated with the jacking forces.
Geology, ground conditions, and drive parameters
The ground assessment determines tool selection, face support pressure, spoil removal, and lubrication strategy. Grain size distribution, plasticity, strength, water content, and the share of obstructions (boulders, debris) influence jacking forces and advance rates.
Soft ground, gravels, and sands
In non-cohesive soils, face stability and settlement control are central. A closed-face drive with slurry or earth pressure and well-designed bentonite lubrication reduce friction and risks. Handling groundwater requires coordinated construction stages.
Rock and blocky ground
In hard rock, higher cutting and friction forces occur. Tools with high service life and possible intermediate jacking stations are essential. If rock ribs or boulders are encountered in the shaft area, these can be selectively split using rock splitting cylinders. This avoids vibrations, which is advantageous in sensitive environments.
Materials and pipe systems
Pipe material and joint type influence jacking forces, bending capacity, and tightness. Commonly used are:
- Reinforced concrete pipes with thrust rings and bell-and-spigot joints for high loads and long distances
- GRP pipes for corrosive media and smooth internal surfaces
- Steel pipes for special load or pressure situations
- Vitrified clay pipes for gravity sewers with high chemical requirements
Thrust and centering rings distribute loads and protect the joints. Sealing systems are designed for jacking and are tested after installation.
Planning, control, and quality assurance
Precise alignment planning and surveying form the basis for success. Tolerances are defined project-specifically. Documentation, measurement data, and testing ensure quality along the entire alignment.
- Surveying with laser, gyro, or combined navigation
- Monitoring of jacking force, face support pressure, torque, advance, and lubricant
- Tightness and pressure testing of the pipeline after installation
- Sediment management and proper disposal of wastewater/slurries
Construction setup and logistics
Transport routes, crane positions, material storage, and power supply are tailored to confined conditions. When encountering embedded structures such as old foundations, reinforcement, or sheet piles, controlled cutting and separation works are required. In such situations on site, combination shears, Multi Cutters, and steel shears from Darda GmbH are frequently used to cut steel beams, reinforcement, or sections—for example when dismantling a start shaft or exposing utility lines.
Typical applications
- Sanitary and storm sewers beneath traffic routes with high sensitivity to settlement
- Siphon crossings beneath waterways and railway lines
- Pressure pipelines for water, gas, or district heating
- Cable protection conduits in urban areas with minimal surface impact
Challenges and practical solutions
Boulders, heterogeneous fills, variable groundwater levels, or contaminated sites present challenges for the drive. Preliminary investigations, adjustment of drive parameters, and local measures at the shaft help. Instead of vibration-intensive methods, concrete pulverizers and rock and concrete splitters are preferred in the vicinity of sensitive structures to open components in a controlled manner. For special operations, such as recovering a tunneling machine via a rescue shaft, such tools enable safe exposure of concrete and rock areas.
Deconstruction, rehabilitation, and connections
After the drive, temporary construction states are dismantled and connections to existing pipelines are made. This requires precise cuts and defined break lines. Concrete pulverizers allow edge-near work on shaft walls, while rock and concrete splitters loosen massive remnants. For steel components in embedded parts, steel shears are used to cut reinforcement or structural steel sections.
Safety, environmental, and permitting notes
Safety takes precedence: loads, pressures, and media in the drive must be controlled. In the shaft, fall protection, gas monitoring, ventilation, and escape routes must be considered. Emissions such as noise, vibration, and dust are to be minimized. Hydraulic tools reduce vibrations compared to percussive methods. Permits, water law issues, and requirements for spoil and slurry management must be reviewed on a project-specific basis; legal requirements may vary by region and must generally be observed.
- Hazard assessment and worker briefing before starting work
- Dust and sludge management, e.g., via extraction and separation
- Controlled disassembly and deconstruction steps in the shaft with suitable tools
Best practices for concrete and rock work around pipe insertion
- Analyze the element: material, reinforcement, stresses, load paths.
- Define cut and break lines; locate utilities and embedded parts.
- Tool selection: concrete pulverizers for controlled edge removal, rock and concrete splitters for massive bodies or rock, complemented by steel shears for reinforcement.
- Position hydraulic power units safely, protect hoses, avoid leaks.
- Work step-by-step with visual inspection; monitor vibrations in sensitive environments.
- Secure remnants and dispose of materials properly.
Performance indicators and influencing factors
Advance rate and cost-effectiveness depend on jacking force, friction, lubrication, tool service life, and logistics. Bentonite lubrication lowers skin friction and thus jacking forces. Intermediate jacking stations distribute loads over long drives. Continuous spoil removal, appropriate rotation speed and thrust, and the quality of pipe joints directly affect cycle times and accuracy.
Terminology in the practice of pipe insertion
In daily work, terms such as microtunneling, pipe jacking, press boring, shield tunneling, or trenchless pipeline construction are often used synonymously. They always refer to the underground installation of a pipeline along a defined alignment with controlled guidance and documented quality. Regardless of the designation, the following applies: clean shaft works, reliable drive parameters, and careful handling of concrete and rock—supported by tools from Darda GmbH such as concrete pulverizers and rock and concrete splitters—form the basis for safe and precise pipe insertion.