Cleanroom deconstruction

Cleanroom deconstruction refers to the professional dismantling and disposal of cleanrooms, cleanroom cells, and adjacent production areas in companies in the pharmaceutical, semiconductor, medical technology, food, and optics industries. The deconstruction is carried out with low emissions, in a structured manner, and under strict control of particles, fibers, aerosols, and vibrations. It covers both structural components (ceilings, walls, floors, foundations) and plant and utility systems. In practice, cleanroom deconstruction combines elements of strip-out and cutting, concrete demolition and special deconstruction. Depending on the task, specialized tools such as concrete pulverizers, stone and concrete splitters, combination shears, multi cutters, steel shears, tank cutters, as well as appropriately sized hydraulic power packs are used, always with a focus on low emissions and controlled process execution.

Definition: What is meant by cleanroom deconstruction

Cleanroom deconstruction is the planned, documented, and controlled removal of components, fit-outs, and technical installations in particle-sensitive areas in which defined cleanliness classes previously applied. The aim is the safe separation and disposal of materials, the prevention of cross-contamination, the preservation of the building structure, and the preparation for conversion, new installations, or decommissioning. Deconstruction typically takes place in segregated zones with negative pressure, air filtration, and airlocks. Procedures and tools are selected to minimize dust, vibration, sparking, and noise. These include in particular hydraulic, cold-cutting and low-vibration methods such as controlled concrete breaking with concrete pulverizers or wedge-based splitting of concrete with hydraulic rock and concrete splitters.

Specific features and requirements in the deconstruction of particle-sensitive areas

Cleanrooms are designed as systems consisting of envelope, airflow, and process equipment. During deconstruction, their interactions must be taken into account: composite materials (e.g., coated sandwich walls), suspended ceilings with integrated luminaires, low-joint floors, service-carrying raised floors, process exhaust, high-purity media (compressed air, nitrogen), cooling water, wastewater, and electrical supply. Components are often chemically burdened (solvents, reaction residues) or biologically contaminated and must therefore be characterized in advance. In execution, low-emission, selective methods are considered state of the art. For concrete and reinforced concrete, depending on accessibility, concrete pulverizers and stone and concrete splitters are suitable; for steel beams, ducts, cable trays, and equipment, combination shears, multi cutters, steel shears, and tank cutters are appropriate. Procedures, protective measures, packaging, and documentation are planned and recorded on a project-specific basis.

Application fields and typical components in cleanroom deconstruction

Cleanroom deconstruction takes place during site conversions, equipment renewals, hall refurbishments, consolidation of room classes, and decommissioning. Typical components and systems include panel walls, doors and airlocks, cleanroom ceilings, luminaires, ventilation ducts, HEPA housings, process fume hoods, floor systems with hard coverings and reaction resins, machine foundations made of reinforced concrete, utility lines, tanks, reactors, and supporting structures. Interventions in the structural shell fall under concrete demolition and special demolition; dismantling within the envelope counts as strip-out and cutting. In particularly confined or secure work environments, deconstruction is carried out as a special operation, for example in ATEX zones, shielded laboratories, or under ongoing production.

Planning, approvals, and project organization

The quality of cleanroom deconstruction is determined in the pre-planning phase. It begins with material flow analysis, hazard assessment, a deconstruction concept, and an approval process with defined responsibilities. Utilities are identified, drained, inerted, or isolated. Component assessments (e.g., reinforcement ratio, material bond) support the choice of methods. The construction process is organized in sections, with intermediate cleanings, cleaning checks, and phased release of areas. Interfaces with building services, fire protection, and building automation are coordinated to ensure that negative pressure, temporary power supply, and emergency routes are safeguarded at all times.

Methods and tools: low dust, low vibration, spark-free

In cleanrooms, low-emission methods have priority. Hydraulic techniques deliver high performance with low excitation of vibrations and without thermal input. The selection and combination of tools depend on component thickness, reinforcement, material mix, accessibility, and the permissible emission limits of the project.

Concrete pulverizers for controlled concrete demolition

Concrete pulverizers crush concrete locally with high clamping force. Advantages in the cleanroom environment include targeted removal, reduced secondary vibrations, and good separability of concrete and reinforcing steel. In combination with point-source extraction, fracture zones can be tightly controlled. For slab openings, wall penetrations, and the deconstruction of machine foundations, concrete pulverizers enable precise geometry without thermal influence—an advantage for adjacent cleanroom areas.

Stone and concrete splitters for crack-guided separation

Stone and concrete splitters use hydraulic wedges or splitting cylinders to split components by inducing pressure cracks. The method is particularly low-vibration and low-dust, as the energy acts within the component and only minimal abrasion swarf is produced. Typical applications include massive foundations, oversized walls, beams, and pedestals near sensitive equipment. The low noise and absence of sparks are advantageous, which is important with sensitive media and in areas with elevated ignition risk.

Hydraulic power packs and attachments

Hydraulic power packs supply concrete pulverizers, splitters, combination shears, multi cutters, and steel shears with pressure and flow on demand. For cleanroom deconstruction, power packs are often placed outside the work zone and connected via hose lines. This externalizes heat and noise; at the same time, handling remains ergonomic in confined airlocks. Oil catchment, drip protection, and quick couplings support clean operation.

Combination shears, multi cutters, and steel shears

For metal components such as beams, frames, cable trays, ducts, or equipment racks, combination shears, multi cutters, and steel shears are suitable. They cut cold, with reproducible cut lines and minimal spark formation. The choice of tool depends on cross-sectional profile, material grade, and accessibility. Through sequential procedures, mixed-material assemblies can be separated and provided as single-fraction streams.

Tank cutters for vessels and containers

In the deconstruction of tanks, special vessels, and large-scale apparatus, controlled, low-spark cuts are essential. Tank cutters enable opening, segmenting, and dismantling of vessels, often in combination with internal cleaning, flushing, and inerting. Sections are dimensioned so that airlocks and lifting equipment can safely accommodate them.

Emission and contamination control

Emission control is the central quality criterion in cleanroom deconstruction. Measures include enclosures, negative pressure, multi-stage filtration, point extraction at the tool engagement zone, mist suppression, wet working methods, dust measurement, and intermediate cleanings. Materials are packaged in dust-tight containers and labeled. Transport routes are short, clean, and separated from each other (clean/unclean). Personnel airlocks and material airlocks structure logistics. Components with potential residual contamination undergo prior decontamination and release.

Occupational safety and legal framework

Protecting employees and the surroundings has top priority. This includes hazard assessments, operating instructions, training, suitable personal protective equipment, and monitoring of noise, dust, and vibration. In sensitive zones, caution is required regarding ignition sources; on the tooling side, low-spark and cold-cutting methods are preferred. Legal requirements arise from generally accepted rules of technology, national regulations, and official specifications; they must be interpreted and observed on a project-specific basis. The information provided here is always general and does not replace case-by-case verification.

Process overview: from enclosure to final cleaning

  1. Survey and material flow analysis: components, media, loads, separation points, logistical routes.
  2. Concept and approvals: deconstruction strategy, emission control, occupational safety, emergency management, inspection steps.
  3. Enclosure and infrastructure: negative-pressure zones, airlocks, temporary power supply, lighting.
  4. Decoupling of utilities: draining, flushing, inerting, electrical isolation, clearance protocols.
  5. Selective deconstruction: strip-out and cutting of equipment, panels, ceilings, ducts, and routes.
  6. Structural reduction: concrete pulverizers and stone and concrete splitters for openings, foundations, and massive components.
  7. Segmentation and logistics: cutting, packaging, labeling, in-plant transport.
  8. Intermediate cleanings and measurements: visual inspection, particle/dust measurements, adjustment of measures.
  9. Final disposal and documentation: single-fraction handover, weigh tickets, recovery and disposal documents.
  10. Final cleaning and release: wet cleaning, filter replacement as per concept, acceptance protocol.

Disposal, recycling, and resource conservation

Separated material streams facilitate recycling and reduce disposal costs. Concrete is preferably broken or split into defined grain sizes; clean reinforcing steel can be sent directly for recovery. Hydraulic methods such as splitting and jaw breaking promote single-fraction purity because there is little thermally induced adhesion. For apparatus and tanks, pre-cleaning, residual material management, and certified documentation must be provided.

Quality assurance, measurements, and documentation

Quality assurance is based on plans, test protocols, and measured values. These include emission measurements, visual inspections, vibration monitoring on sensitive neighboring equipment, cleaning records, and releases of construction sections. Comprehensive documentation creates transparency for the client, authorities, and subsequent trades and forms the basis for restoring defined room qualities.

Special challenges and special scenarios

Demanding scenarios include deconstruction during ongoing production, work in small airlocks with limited lifting equipment, deconstruction in potentially explosive areas, and tasks with potentially hazardous residual substances. Compact, hand-held hydraulic tools and methods with minimal emissions have proven their worth here. Crack-guided splitting of massive components and locally confined breaking with concrete pulverizers reduce vibrations, protect neighboring processes, and keep downtime short.

Selection criteria for methods and equipment

  • Component parameters: thickness, reinforcement ratio, material bond, installation situation.
  • Environmental requirements: permissible particle/dust emission, noise, vibration, temperature.
  • Safety aspects: ignition sources, residual media, structural constraints, escape and rescue routes.
  • Logistics: access, airlock dimensions, load capacities, routing, lifting gear.
  • Target condition: opening geometries, reuse of adjacent components, cleaning level.
  • Sustainability: single-fraction purity, recyclability, energy input.

Interfaces to structural shell and technical building services

Cleanroom deconstruction affects the load-bearing structure, fit-out, and building services. Separation points for ventilation, cooling, heating, media, electrical systems, and building automation must be clearly defined and secured. Openings in slabs and walls are statically assessed and created using low-emission methods. For massive concrete components, concrete pulverizers for precise removal and stone and concrete splitters for quiet opening are a proven combination.

Relation to application areas and products in the cleanroom context

Cleanroom deconstruction brings together several application areas: concrete demolition and special demolition for interventions in the structural shell and foundations; strip-out and cutting for dismantling of fit-out and equipment components; special operations where emissions are restricted or specific hazards exist. Depending on the task, the tool spectrum includes concrete pulverizers, stone and concrete splitters, hydraulic power packs, combination shears, multi cutters, steel shears, tank cutters and—where massive natural stone or concrete composites are present—stone splitting cylinders as well. Selection always follows the principle: as much power as necessary, as little emission as possible.

Sustainability and value preservation of adjacent areas

Low-emission methods protect not only people and processes but also the building fabric. Precise deconstruction cuts, crack-guided splitting, and localized breaking prevent consequential damage, shorten cleaning phases, and improve the reusability of adjacent components. This has a positive effect on schedule, costs, and environmental footprint.