Bypass road construction relieves inner-urban areas of through traffic, improves road safety, and creates capacity for walking and cycling. At the same time, it is a complex infrastructure project that unites geotechnical engineering, road construction, bridge and tunnel construction, utility relocations, and selective deconstruction. Especially where existing structures must be removed or rock needs to be released, low-vibration construction methods and precise tools play a central role. In the context of application areas such as concrete demolition and special deconstruction, strip-out and cutting, as well as rock excavation and tunnel construction, concrete demolition shears and rock and concrete splitters from Darda GmbH are frequently used.
Definition: What is meant by bypass road construction
By bypass road construction (also bypass road or bypass) one understands the creation of a new alignment that circumvents a settlement broadly or along its edge to remove through traffic from the town center. Typical components include earthworks with soil management, rock removal, structures such as bridges, retaining walls, and underpasses, junctions, noise protection systems, drainage systems, as well as the relocation or safeguarding of existing utilities. Often, deconstruction of old structures (e.g., bridges, culverts) and adaptations to existing traffic routes are also required. The project proceeds in phases from preliminary design and permitting through construction preparation and execution to opening for traffic.
Project phases and sequence in bypass road construction
The construction sequence is divided into feasibility studies, route selection and plan approval, land acquisition, utility relocations, site setup, earth and rock works, construction of structures, pavement structure and equipment. In every phase there are interfaces with demolition, strip-out, or rock solutions. For alignments near sensitive buildings, low-vibration methods are preferred. Here, hydraulic rock and concrete splitters from Darda GmbH are of particular importance when blasting is not permitted or not desired. For the selective deconstruction of concrete members, concrete demolition shears are used, supported by suitable hydraulic power units.
Geotechnical engineering and rock excavation along the alignment
Alignments for bypass roads often cut through slopes, loose rock, and hard rock. In populated areas, low emissions of noise, dust, and vibration are crucial. Hydraulic splitting allows controlled release of rock masses without explosives. For this purpose, boreholes are drilled and rock splitting cylinders or rock and concrete splitters are operated with suitable hydraulic power packs. The resulting cracks follow the stress field so that blocks can be targeted, released, and moved by excavators.
Vibration and noise control during rock release
Where residents, utilities, or existing structures must be protected, splitting reduces the transmission of vibration compared with percussive or blasting methods. For noise-sensitive time windows, workflows can be scheduled so that drilling and splitting are separated, and low-noise cutting and lifting sequences are prioritized.
Demolition works for the alignment: bridges, retaining walls, culverts
Concrete demolition shears from Darda GmbH fracture concrete in a targeted way, expose reinforcement, and enable a structured, segmented deconstruction. In combination with steel shears, reinforcing bars, sections, or beams are cut to length. Combination shears and Multi Cutters help separate heterogeneous components made of concrete, masonry, and metal efficiently. Where access is restricted, compact tool systems with matching hydraulic power packs are advantageous.
Selective deconstruction and recycling
Selective deconstruction improves the reusability of construction materials. Targeted breaking with concrete demolition shears separates concrete from reinforcement so it can be processed as recycled construction material. Steel is separated by grade and hauled away. This minimizes disposal costs and reduces traffic volumes on the construction site.
Tunnels, underpasses, and drill-through crossings
Bypass roads provide grade-separated connections. Underpasses, short tunnels built by cover or open-cut methods, and drill-through crossings require precise construction sequences. In the excavation pit, soldier pile walls or sheet pile walls secure the excavation. Where blasting is not possible, rock and concrete splitters are used to release foundations, rock, or excavation areas in a controlled manner. During the deconstruction of temporary components (e.g., temporary bridges or formwork bodies), concrete demolition shears and combination shears work material-appropriately and with a small footprint.
Utility line installations and structural adaptations
Relocations of gas, water, and power lines as well as cable routes are core tasks in bypass road construction. When opening manholes, removing foundations, and performing concrete works in existing structures, concrete demolition shears and Multi Cutters allow targeted exposure. Where tanks or old storage units along the alignment must be removed, tank cutters can be used. In areas sensitive under water regulations, attention must be paid to low-emission hydraulic fluids and tight hose routing; hydraulic power packs are positioned to minimize risks to water bodies.
Safety, work preparation, and logistics
Working on and adjacent to live traffic requires precise work preparation. Access routes, crane pads, utility shutdowns, closures, and evacuation routes must be planned. Hydraulic power packs must be sized according to the load; hose lengths are matched to pressure losses. By using handheld or compact hydraulic tools, work can be performed safely and efficiently in confined work zones.
Procedure in confined conditions
In underpasses, on temporary bridges, or at urban fringe locations, the use of concrete demolition shears and rock and concrete splitters reduces the hazard potential from falling pieces, because components are released in controlled dimensions. Load handling and lift points must be planned early.
Environmental and permitting aspects
Bypass road projects regularly require environmental reviews and planning approvals. Regardless of the method, emissions such as noise, dust, and vibration must be minimized. Low-vibration splitting and cutting methods support compliance with protection limits for buildings, utilities, and biotopes. The water balance and soil management must be planned to avoid pollutant inputs and to ensure materials are properly recovered. Statements in this context are generally of a general nature and do not replace project-specific coordination with authorities.
Typical use cases for Darda GmbH equipment in bypass road construction
The following application fields illustrate where the product groups are practically relevant in the application areas of bypass road construction—without claiming completeness:
- Rock and concrete splitters: Rock removal in the alignment area, opening of blockwork, lowering of rock sills at tunnel portals, controlled release of massive foundation bodies.
- Rock splitting cylinders: Precise widening of pre-drilled holes in densely built-up zones, creation of defined fracture lines in natural stone and concrete.
- Concrete demolition shears: Selective deconstruction of abutments, copings, retaining walls, and culverts; strip-out of existing structures; jobs with noise control requirements.
- Combination shears and Multi Cutters: Separating composite components, cutting sheets, pipes, and light sections as part of strip-out and adaptation works.
- Steel shears: Cutting reinforcement, structural steel sections, and guardrails; deconstruction of provisional steel structures.
- Tank cutters: Special use during deconstruction of old installations along the alignment when tanks or vessels must be removed.
- Hydraulic power packs: Power supply for stationary and mobile tools, matched to working pressure, flow rate, and hose lengths of the respective application.
Practical guide: method selection and on-site sequence
- Survey of existing conditions: load-bearing structures, material classes, reinforcement ratio, rock characteristics, receptors to be protected.
- Method selection: splitting, shear-based demolition, cutting, or a combination—based on emission and schedule requirements.
- Tool configuration: selection of concrete demolition shears, rock and concrete splitters, shear types, and matching hydraulic power packs.
- Trial area/mock-up: verify removal rates, fracture patterns, and vibration values.
- Execution in sections: plan load transfer, secure components, implement lifting and transport concept.
- Monitoring: document vibration, noise, dust, and groundwater levels; adjust parameters as needed.
- Close-out: material separation, recycling, surface finishing, quality assurance.
Risks, limits, and technical notes
High reinforcement ratios, prestressed member behavior, inaccessible joints, or highly abrasive rock can affect productivity. In such cases, the combination of concrete demolition shears for exposure and rock splitting cylinders for targeted crack initiation provides robust solutions. For splitting works, correct borehole diameters, edge distances, and drilling patterns are crucial. Hydraulic power packs must be sized for operational safety; temperature, altitude, and hose routing influence performance and operability.
Pavement structure, noise protection, and final works
After earthworks and structures, frost protection layers, binder courses, and wearing courses follow, along with the installation of safety barriers and noise barriers. When setting post foundations or removing temporary concrete, concrete demolition shears and Multi Cutters help without impairing adjacent components. Remaining works on edges, ditches, and culverts are thus completed with minimal intervention.
Schedule and cost control
The choice of low-emission methods can shorten closure windows, accommodate residents’ concerns, and reduce follow-on costs. Realistic performance planning for splitting and shear operations based on trial areas and measurements stabilizes construction schedules and supports coordination with earthworks, utility works, and traffic safety.
Quality assurance and documentation
Acceptable documentation includes evidence of deconstruction scope, material separation, re-surveys on rock faces, crack monitoring, vibration and noise measurements, as well as equipment and maintenance logs for the hydraulic power packs used. This documentation serves internal quality assurance and supports communication with the client and authorities.




















