An effective construction emergency plan structures the emergency organization, assigns responsibilities, and defines clear procedures—from the first alarm through to resuming work. Especially for activities such as concrete demolition, special demolition, building gutting, rock excavation, and tunnel construction, where hydraulic shear and hydraulic wedge splitter methods are used, a robust plan is crucial. Practice shows: those who predefine scenarios, reporting paths, evacuation, rescue, and communication reduce risks and maintain the ability to act—even under pressure. This applies in particular when concrete demolition shear, hydraulic wedge splitter, or other hydraulic shear and hydraulic wedge splitter technology from Darda GmbH are used.
Definition: What is meant by a Construction Emergency Plan
A Construction Emergency Plan is a structured, written concept for construction projects that describes preventive, organizational, and technical measures to handle disruptions, accidents, and critical events. It includes, among other things, alarm and reporting paths, evacuation and rescue processes, responsibilities, communication rules, provision of emergency equipment, and the integration of external parties. In high-risk work areas—such as selective deconstruction with concrete demolition shear, controlled splitting of concrete or rock, and steel cutting—additional activity-specific modules are integrated. The goal is to minimize damage to people, environment, structure, and equipment and to accelerate the restoration of a safe construction state.
Structure and contents of an effective emergency plan
A robust emergency plan on the construction site follows a clear structure that is applicable in day-to-day operations and remains intuitive under stress. Core elements are:
- Hazard analysis with a hazard matrix: identification of typical scenarios (e.g., risk of collapse during concrete demolition, uncontrolled movements during rock excavation, hydraulic leaks, fire events at the hydraulic power pack, hazardous substance release during building gutting).
- Alarm and reporting plan: internal and external reporting chain, alarm activation, responsibilities for the initial report and follow-up alerts.
- Evacuation and rescue concept: assembly points, escape routes, airlock areas (tunnel construction), rescue from pits/trenches, accessibility for emergency services.
- Roles and responsibilities: site management, safety and health coordination, emergency coordinator, first aiders, fire wardens, signallers.
- Technical and organizational measures: shutdowns, securing, barriers, emergency stop, energy isolation states, approval processes after a disruption.
- Communication during the event: clear language, defined points of contact, documentation, information sharing with project participants.
- Emergency equipment and infrastructure: first-aid materials, extinguishing agents, absorbents, respiratory protection according to the hazard analysis, reserve systems (e.g., hydraulic hose line).
- Training and drills: briefings, exercises, lessons learned, plan updates.
Legal framework and standards (general, non-binding)
Legal requirements for emergency organization and occupational safety may vary by country, state, and project. Generally relevant are provisions on occupational safety, construction site regulations, handling hazardous substances, fire and explosion protection, traffic safety, and environmental and water protection. Generally accepted rules of technology, applicable standards, and guidelines can provide orientation. Project managers should ensure the emergency plan is consistent with the hazard analysis, construction site rules, and the safety and health plan.
Typical risks in construction: concrete demolition, building gutting, rock excavation, tunnel construction
The risk profile varies with methods and environment. In areas where products from Darda GmbH are used, the following hazards typically occur:
Concrete demolition and special demolition
- Concrete demolition shear: falling concrete pieces, springback of reinforcing steel, crushing and shear points, dust and fragments, dynamic load redistribution.
- Hydraulic wedge splitter for stone and concrete: spontaneous crack propagation, stress redistribution, projectile effect of small fragments, unexpected component movements.
- Hydraulic power pack: noise emission, exhaust gases depending on drive, overheating, oil mist, fire load, high-pressure leaks.
Building gutting and cutting
- Release of dust, potentially contaminated dusts, noise, vibrations, hidden utility line, residual energies in components.
- Combination shears, multi cutters, steel shear: loss of structural stability during separation, cut edges as a hazard source.
Rock excavation and tunnel construction
- Rock breakout, rockfall, uncontrolled block movements, confined spaces, limited escape and rescue routes.
- Rock wedge splitter: controlled splitting requires stable shoring and exclusion zones to avoid secondary movements.
Alarm, evacuation, and rescue chain
An effective rescue chain is defined in advance and known to the crew. Depending on the site, redundant communication means are useful. Basic principles:
- Trigger the alarm, secure the danger area, inform first aiders and emergency coordination.
- Evacuate via defined escape routes to assembly points, check attendance.
- Initiate life-saving immediate measures, and in parallel alert external rescue per project specifications.
- The signaller clears the access route and hands over structured situational information to rescue services.
- Aftercare: secure the area, root cause analysis, approval before restart.
Technical emergency measures for hydraulic splitting and cutting methods
Concrete demolition shear: stability and exclusion zones
- Preliminary structural analysis of the components; have shoring ready, use retention system, define and mark exclusion zones.
- In case of uncontrolled component movement: stop work, clear the area, reassess the load-bearing behavior, block access.
- Dust and fragment control: depending on assessment, consider shielding, suitable PPE, misting or a water spray system, or dust extraction plant.
Hydraulic wedge splitter for stone and concrete: controlled energy release
- Document drilling pattern and splitting sequence for controlled splitting with rock and concrete splitters; in case of unplanned crack formation: interrupt the splitting, expand the danger area.
- Monitor hydraulic pressure; ensure pressure release at the end of work, make tools pressure-free.
- With jammed tools: do not apply force; systematically relieve loads, provide additional securing of the surroundings.
Hydraulic power pack and lines
- Define emergency stop and shutdown sequence for the safe operation of hydraulic power units; train fire and leakage scenarios.
- High-pressure leakage: clear the area, reduce pressure, absorb fluid release with absorbents, organize disposal via a certified disposal company.
- Hose burst: redundant supports, protective sleeves, visual inspection; after the event, no further operation without approval.
Scenario modules for the emergency plan
Accident with a person trapped during deconstruction
- Immediate shutdown of the hydraulics, depressurize, secure tools.
- Rescue only by trained personnel; shore additional loads, avoid secondary risk of collapse.
- First aid, documentation, lockout until approval.
Component tips or collapses unexpectedly
- Clear the zone, provide temporary stabilization, repeat structural assessment.
- Adjust the demolition sequence, extend barriers.
Fire/overheating at power units
- Provide suitable extinguishing agents; minimize fire loads, consider ventilation.
- After successful extinguishing: do not operate the hydraulic power pack, perform root cause analysis.
Hazardous substance release during building gutting
- Stop work, seal the area, continue only under defined protective measures.
- Organize disposal and cleaning according to project specifications.
Coordination with third-party companies and interfaces
Where multiple companies are active simultaneously, interface coordination is central. The emergency plan defines communication paths, responsibilities, and common rules—for instance, during parallel demolition works, cutting activities, and transports. Interfaces to internal approvals, lockouts, energy control, and traffic management on the construction site are defined.
Training, instruction, and drills
Knowledge and routine determine success during an event. Instructions cover hazards, reporting paths, and the practical use of emergency equipment. Regular drills—including unannounced ones—test alarm activation, evacuation, briefing of rescue services, and technical shutdown measures. Insights flow back into the plan as improvements.
Emergency equipment and material provision
- First aid: dressings, eye wash, stretcher, heat retention, marking of locations.
- Firefighting: suitable fire extinguishers by class, possibly fire blankets.
- Leakage control: absorbents, drip trays, sealing cushions, waste containers for disposal.
- Barriers: tapes, fences, lighting for night operations, signage.
- Tool-specific: spare hydraulic hose line, protective caps, shoring material, wedges, pads.
Environmental and water protection in emergencies
Hydraulic fluid and lubricants must not enter soil or water bodies. The emergency plan includes measures for rapid containment and absorption, defines collection points, and the waste management chain. When working in tunnel construction or sensitive landscapes, additional retention system and organizational precautions are provided.
Documentation and continuous improvement
Every event is documented in a structured way: time, location, participants, equipment involved (e.g., concrete demolition shear, hydraulic wedge splitter), weather, sequence, and measures taken. Debriefings identify causes and potential improvements. The plan is version-controlled; changes are communicated and instructed.
Integration with construction sequence and the safety and health plan
The emergency plan is synchronized with the schedule, construction phases, traffic routing, and logistics. Construction states, load redistributions, and lockouts from the deconstruction concept are represented. Interfaces with the safety and health plan are aligned, as are responsibilities during night or weekend work.
Practical guide: creating a Construction Emergency Plan
- Project analysis: record activities, methods, equipment (including hydraulic wedge splitter and hydraulic shear technology from Darda GmbH).
- Hazard analysis: prioritize scenarios, define protective measures, plan exclusion zones.
- Organization: define roles, contactability, deputies, on-call arrangements.
- Procedures: alarm plan, evacuation, rescue, technical shutdown, restart criteria.
- Resources: equipment, escape routes, assembly points, access routes, lighting, redundancies.
- Communication: reporting steps, information chains, documentation forms.
- Training and drills: test the plan, eliminate weaknesses, update the plan.
Special considerations for special operations
In special operations—such as time-critical measures, work in confined spaces, at height, or cutting on tanks—additional approvals and control steps must be provided. For tank cutting—for example, using the Tank Cutter—atmospheric conditions, ignition source control, and gas-free measurements must be regulated in coordination with project requirements and any applicable ATEX zone. The emergency plan addresses the risk of rapid changes in the situation and places higher demands on barriers, measuring, and firefighting technology.
Quality criteria for a robust emergency plan
- Clarity: simple, unambiguous language, flow cards supported by graphics.
- Accessibility: available everywhere, updated, versioned, instructed.
- Realism: procedures reflect actual construction site conditions.
- Scalability: suitable from minor incidents to major damage.
- Compatibility: consistent with the deconstruction concept, construction logistics, fire protection, and environmental requirement (construction).
Role clarity for work with concrete demolition shear and splitting technology
For activities with concrete demolition shear, hydraulic wedge splitter, or rock wedge splitter, responsibilities must be defined with particular clarity. Operators, riggers, safety watch, and emergency coordinator know their tasks, especially in the event of unexpected component movements. Stop signals and emergency stop are standardized; visual contact or secure radio channels are bindingly defined.
Communication and crisis management
In an event, calm, structured communication is what counts. The emergency plan defines key messages, contacts, and escalation levels. Internal and external information is fact-based, concise, and comprehensible. After the acute phase, internal information, root cause analysis, and action planning follow to restore trust and safety.