Gutting works

Gutting works are the precise, selective deconstruction within existing structures: fit-out elements, installations, and non-load-bearing components are removed in a controlled manner so that refurbishment, renovation, or subsequent partial demolition can proceed safely and efficiently. The focus is on low-emission methods, source-separated material flows, and the protection of the load-bearing structure. Handheld hydraulic technology—such as concrete pulverizers as well as concrete splitters with matching hydraulic power units—enables low-vibration and quiet operations that are particularly in demand indoors, in sensitive environments, and where space is restricted.

Definition: What is meant by gutting works

Gutting works refer to the selective strip-out of interior components and building services up to the load-bearing structure of a building. This includes, for example, floor coverings, suspended ceilings, lightweight partitions, windows and doors, service runs, technical building equipment, as well as locally confined concrete and masonry areas. The aim is the preparatory exposure for repurposing, renovation, or subsequent concrete demolition and special deconstruction. Characteristic features include a clear sequence of investigation, planning, material separation, and documented execution, as well as the use of low-vibration and low-dust methods such as concrete pulverizers, rock wedge splitters, and other hydraulic tools.

Process and planning of gutting works

Systematic planning structures the deconstruction into logical steps: from the condition survey through the deconstruction concept to source-separated disposal. As early as the concept phase, it is determined which components will be removed in which sequence, how material flows will be managed, and where hydraulic power packs with concrete pulverizers or concrete splitters will be deployed to minimize noise, dust, and vibration.

Preliminary investigation and deconstruction concept

The starting point is existing documentation, site walk-throughs, and, where required, the investigation of potential hazardous substances. Structures are assessed with regard to temporary shoring. Utilities are systematically isolated, and lines are marked. The deconstruction concept prioritizes the removal of easily demountable components and governs the step-by-step approach to the structure—including defined separation cuts and splitting directions in the concrete.

Site setup and protective measures

Access control, material routes, dust protection, and fire protection are set up to suit the project. For work in existing buildings, the use of compact hydraulic power packs has proven effective; they use electrical supply and, due to their small dimensions, can be positioned on upper floors and in basements. Measures for dust suppression, noise reduction measures, and ground vibration monitoring support sensitive work in the vicinity of components worthy of protection.

Selective removal and material separation

The removal follows the principle “from light to heavy” and “from outside to inside”: dismantling, separation, intermediate storage, and transport are coordinated. To ensure high-quality recycling, material flows are separated early.

  1. Dismantling of finishes, fixtures, and installations
  2. Deconstruction of lightweight partitions and substructures
  3. Targeted openings and separation cuts in massive components
  4. Size reduction and transport, ongoing documentation

Technical deconstruction of load-bearing components in the interior

Where massive components must be segmented, concrete pulverizers are used for controlled breaking of edges and locally confined areas, and concrete splitters or rock wedge splitters are used for low-stress splitting of concrete. Reinforcement and profiles are cut with combination shears, Multi Cutters, or steel shears. Power is supplied by suitable hydraulic power packs. This approach reduces vibration and secondary damage and allows a step-by-step, dimensionally accurate procedure.

Tools and technology in focus

The choice of tool depends on component thickness, reinforcement density, accessibility, and environmental requirements. Handheld hydraulic systems are established in gutting because they are compact, powerful, and easily controllable.

Concrete pulverizers

Concrete pulverizers grasp component edges, beam ends, or slab borders and crush the material step by step. Advantages include precise metering of removal, spark-free operation, and the option to cut reinforcement with complementary shears. Selection criteria include grip range, crushing force, accessibility, and compatibility with the hydraulic power pack. Typical applications are openings in slabs and walls, exposing connections, and removing local reinforcements.

Rock and concrete splitters

Rock and concrete splitters generate very high forces via hydraulic wedge splitters in previously drilled core holes. The concrete is split along planned lines—with low vibration and low noise. This is ideal for thick walls, foundations, plinths, and areas where vibration must be limited. Borehole geometry, the split pattern, and the sequence of cylinders produce the desired crack pattern. For natural stone or heavily reinforced components, splitting and cutting operations can be combined.

Hydraulic power packs

Hydraulic power packs provide pressure and flow rate for pulverizers, splitters, and shears. For gutting works, compact, electric-powered units with adequate power reserves are common. Important aspects include hose management, couplings, operating noise, and the ability to change tools quickly. Clean hydraulics reduce downtime and increase the repeatability of work sequences.

Combination shears, Multi Cutters and steel shears

Combination shears combine gripping and cutting and are suitable for mixed layers of concrete debris and reinforcement. Multi Cutters are designed for versatile cutting tasks on profiles, cable trays, or thin-walled components. Steel shears focus high cutting force on load-bearing steel such as beams or reinforcement bundles. Their low-spark operation is an advantage over thermal cutting methods in sensitive interior areas.

Tank cutters and special operations

Tank cutters are designed for safe cutting of vessels and hollow bodies, for example during the dismantling of technical plant. In special operations, they are combined with concrete pulverizers, splitters, and shears to solve complex separation tasks in a material-appropriate and low-emission manner.

Areas of application and typical use cases

Gutting works form the basis for numerous applications. The following areas show typical focal points and the interplay of the tools:

  • Concrete demolition and special demolition: Segmenting reinforced concrete prior to haulage with concrete pulverizers; controlled splitting of massive components using rock wedge splitters and concrete splitters; cutting reinforcement with steel shears.
  • Gutting works and cutting: Openings and breakthroughs in existing structures, edge-accurate removal with concrete pulverizers; additionally cutting profiles and services with Multi Cutters or combination shears.
  • Rock excavation and tunnel construction: In side chambers or shafts, rock wedge splitters enable low-vibration solutions when heavy equipment cannot be used.
  • Natural stone extraction: Splitters create defined separation joints in natural stone without thermally or dynamically stressing the material.
  • Special operation: Dismantling plant components and vessels with tank cutters; combined methods for complex material composites.

Quality, environmental, and safety aspects

Quality in gutting means clean separation cuts, minimized secondary damage, and structured material logistics. Environmental aspects include low-dust working, the reduction of noise emissions, and construction waste sorting for recycling. Safety is based on qualified personnel, appropriate personal protective equipment, and procedures that respect the residual load-bearing capacity. Legal requirements and technical rules must be considered for each project; the following measures have proven effective.

Dust, noise, and vibration management

  • Dust suppression through adjusted work sequencing, targeted wetting of materials, and efficient dust extraction at the source
  • Low-noise methods by using concrete pulverizers and splitters instead of impact tools wherever possible
  • Low-vibration work with rock and concrete splitters; ground vibration monitoring in sensitive neighboring areas
  • Logistics with short transport routes, closed containers, and clear traffic routes

Structural and fire protection aspects

Temporary shoring secures components during deconstruction. When working on fire-protection-relevant components, compensatory measures are planned. Hydraulic crushers and shears operate without sparks; for activities with potential ignition sources, special precautions apply. The approach is coordinated with the project’s fire protection concept.

Practice: Step-by-step procedure

  1. Record existing conditions, isolate utilities, verify structural boundary conditions
  2. Develop the deconstruction concept, define material flows and protective measures
  3. Site setup, dust and noise control, install shoring
  4. Selective removal of finishes, fixtures, and installations
  5. Create local openings; segment components with concrete pulverizers or splitters
  6. Cut reinforcement, profiles, and services with combination shears, Multi Cutters, or steel shears
  7. Remove material in a source-separated manner, organize intermediate storage, keep records
  8. Quality control, cleaning, documentation, and handover

Typical challenges and solutions

Confined access, sensitive neighboring structures, and unknown embedded elements are typical in gutting within existing buildings. Solution: modular hydraulics with compact power packs, early exploratory surveys and trial areas, step-by-step segmentation with concrete pulverizers, and targeted splitting lines with rock wedge splitters. In heavily reinforced zones, combining splitting with subsequent cutting of reinforcement using steel shears accelerates the process. In areas sensitive to hazardous substances, the method is adapted to the required protective measures.

Documentation and verification

Clear documentation creates transparency: plans with deconstruction stages, photo logs, records of material flows, and emission measurements form the basis for quality assurance and acceptance. Maintenance and inspection records of the deployed hydraulic power packs as well as of the concrete pulverizers, splitters, and shears support low-disruption operation and traceability of results.