A tunnel support secures, during the excavation advance or when working in existing structures, the surrounding rock mass and the lining structure against deformation and collapse. It acts as a load-bearing element between the crown, springline, and invert, distributes loads, and keeps clearances open for logistics and installation processes. In practice, the spectrum ranges from temporary supports in the early phases of shotcrete lining to permanent components that become part of the inner lining. In conjunction with shotcrete, anchors, and lattice girder beams, the tunnel support forms a system that governs safety, construction progress, and quality. During construction and deconstruction phases, tools by Darda GmbH are frequently used, such as concrete pulverizers or rock and concrete splitters, when concrete or rock areas need to be released, separated, or adjusted in a controlled manner.
Definition: What is meant by tunnel support
A tunnel support is a load-bearing element that, in tunnel construction, takes loads from rock pressure, self-weight, and, where applicable, water pressure and transfers them into the ground or adjacent lining components. Tunnel supports can be temporary to secure individual construction phases or permanent as part of the final lining. Common forms include steel arches and lattice girder beams, shotcrete ribs connected to rock or concrete anchors, as well as hydraulic props as an auxiliary measure. Unlike purely surface linings (e.g., inner linings), tunnel supports act primarily as supporting and bracing elements and are designed and installed depending on the excavation method (e.g., conventional/NATM, drill-and-blast, or machine-driven).
Structure and mode of action of modern tunnel supports
Modern tunnel supports often consist of preformed steel arches or lattice girder beams that are complemented with shotcrete and anchors to form a composite system. Base plates or invert connections ensure force transfer into the invert layer, while head plates, lugs, or gusset plates provide a contact-stiff connection to the crown and calotte. Decisive is load path clarity: compressive forces must be carried without risk of buckling and without inadmissible point loads. With hydraulic supports, the initial force is introduced via controlled preloading to limit settlements in the early phase. Survey marks and convergence measurements record deformations; if thresholds are exceeded, the lining is adjusted or supplemented.
Types and materials of tunnel supports
Steel arches and lattice girder beams are particularly widespread, as they carry high loads and interlock well with shotcrete. Shotcrete ribs with reinforcement act as surface-supporting elements and can merge into an integral support together with head anchors. Historically, timber supports were also used; today, they are more the exception for short-term auxiliary measures. Hydraulic props serve as temporary shoring, for example under the calotte or during alterations in existing structures. Materials generally include structural steels, reinforced shotcrete, occasionally fiber-reinforced concrete for crack control, and corrosion protection systems. Fire resistance and corrosion resistance are central design aspects for permanent supports.
Planning and design in the context of the advance
The dimensioning of tunnel supports is based on geotechnical investigation, rock mass classification, and hydraulic boundary conditions. Typical load cases include short-term and long-term capacity, construction states during staged excavation, vibrations, temperature, and water. Convergence–confinement approaches, numerical models, and observational methods (monitoring) are combined. Safety concepts consider settlement reserves and retrofit options. Legally, the recognized rules of practice and applicable standards must be followed; project-specific requirements of clients and authorities must also be observed.
Installation sequence and synchronization with the advance
Installation is synchronized with the excavation cycles: excavation, crown stabilization (e.g., pipe umbrella or spiles), anchors, setting up the support, composite with shotcrete, and subsequent invert construction. Tolerances in axial position, inclination, and connection details are to be checked; bearing pads or wedges ensure a full-surface fit. For cross-section adjustments or clashes with installations, concrete or rock is selectively removed in a controlled manner. Here, concrete pulverizers by Darda GmbH are helpful for low-vibration reworking of shotcrete ribs, edges, or fillets. Rock and concrete splitters enable targeted opening of concrete foundations or invert sills without shaking the surrounding rock mass. Hydraulic power units provide the power supply for these tasks in confined tunnel cross-sections.
Interfaces with excavation methods
In conventional excavation (NATM), tunnel supports are closely combined with shotcrete and anchors to control rock deformation early. In drill-and-blast excavation, robust connection details and a coordinated time window between excavation, ventilation, and installation are essential. In machine-driven excavation, segment rings assume the primary load-bearing role; tunnel supports are then used for niches, cross passages, or connecting structures. During phase shifts, gutting, or enlargements, supports are deployed as temporary support until the final lining is in place.
Maintenance, strengthening, and rehabilitation
Over the service life, tunnel supports must be checked for corrosion, section loss, loss of contact, and deformations. Strengthening measures include additional ribs, node reinforcements, subsequent anchoring, or replacement of damaged components. In existing structures, selective concrete removal is often required, for example to expose connection points. Concrete pulverizers by Darda GmbH are suitable for this because they separate in a controlled manner and expose the reinforcement. For massive blocks or cold joints, rock splitting cylinders and rock and concrete splitters can initiate cracks that enable low-damage lifting. Steel components such as lattice girder beams or head plates are cut with steel shears, combination shears, or Multi Cutters to maintain construction phases without sparks or excessive vibration.
Deconstruction of tunnel supports in existing assets
When deconstructing in operational or existing facilities, stability has priority. The procedure is carried out section by section: prop, unload, cut, remove, re-secure. For separating shotcrete composites, concrete pulverizers are suitable; anchor heads are exposed and released according to the plan. Steel supports are cut out using steel shears or Multi Cutters before invert embedments are removed. Rock and concrete splitters minimize vibration, which is particularly advantageous for sensitive neighboring structures and in concrete demolition and special deconstruction. In confined situations (special deployment), the combination of compact tools and hydraulic power packs offers a practical solution to avoid disturbing load paths and to limit dust and noise emissions.
Occupational safety, environmental and health protection
Safety begins with robust temporary state planning, gas and dust management, and reliable ventilation. Personal protective equipment, reliable rescue routes, and clear communication rules are mandatory. Low-vibration methods and controlled separation techniques reduce vibrations and lower risks for adjacent structures. Segregated material logistics (steel, concrete, rock) facilitate recycling and disposal. In water-bearing strata, pressure and sealing measures must be considered before releasing supports; interventions are carried out only after approval by the site management.
Typical use cases
Common applications include temporary support of the calotte in swelling formations, securing of connection adits, cross-section enlargement in existing bores, and rehabilitation of corroded steel arches. During gutting and cutting in existing structures, attachments, cable trays, or foundation remnants are removed before new support or lining systems are installed. Concrete pulverizers and rock and concrete splitters by Darda GmbH support these steps with controlled cutting and splitting processes tailored to the surroundings. In natural stone extraction and in rock excavation and tunnel construction, tunnel supports are also used as temporary stabilization in exploration headings and cross-cuts until the final lining is completed.
Terms and distinctions in the tunneling context
In common usage, tunnel supports are sometimes referred to as lining or support arches, whereas the surface lining is provided by shotcrete and the inner lining. Crown support (Firststütze) specifically means the support of the calotte; ribs and struts connect supports into a frame. The final lining often consists of a watertight inner lining, while the support bridges construction states or remains part of the composite system. These distinctions help define tasks, refine design, and select suitable tools—such as concrete pulverizers, rock splitting cylinders, or steel shears—for construction, strengthening, and deconstruction.




















