Heavy haulage

Heavy haulage is the invisible backbone of many projects in deconstruction, in natural stone extraction, and in industrial conversion. Without safe loading and thoughtful route planning, neither machines nor large components arrive at their place of use in time. Especially in connection with concrete pulverizers as well as rock and concrete splitters from Darda GmbH – for example during the removal of pre-segmented components or the feeder transport of hydraulic power packs, combination shears, steel shears, multi cutters, and tank cutters – precise haulage logistics determines cycle times, costs, and occupational safety.

Definition: What is meant by heavy haulage

Heavy haulage refers to the transport of goods that exceed the regular limits of road traffic in terms of mass and/or dimensions. Typical are high gross weights, large lengths, widths, or heights as well as special requirements regarding axle load distribution, cornering, bridge crossings, and clearance heights. In the context of concrete demolition and special deconstruction, strip-out and cutting, rock excavation and tunnel construction, natural stone extraction, and special missions, this concerns both the transport of equipment (e.g., rock splitting cylinders, hydraulic power packs, concrete pulverizers) and the movement of extracted or pre-segmented loads (concrete segments, natural stone blocks, steel assemblies, tank segments).

Planning and permits in heavy haulage

Heavy haulage begins long before the first movement of the load. A technical assessment of the cargo, the selection of suitable vehicles, a route survey, and obtaining the required official permits and conditions are necessary. Requirements for driving times, escort vehicles, signage, lighting, and safeguarding vary regionally and must always be checked on a case-by-case basis. Statements on this are general and non-binding; the final requirements result from the notices issued by the competent authorities.

Preliminary survey and route analysis

The routing is adapted to cargo geometry and weight. With a view to concrete and rock segments created using concrete pulverizers or rock and concrete splitters, edges, center of gravity, and positive fit must be taken into account. Key checkpoints:

  • Clearances/approvals for bridges, culverts, roundabouts, underpasses, and temporary construction provisions
  • Curve radii, widened curves, turning and maneuvering areas at loading and unloading points
  • Load-bearing capacity and condition of the subgrade (e.g., roadway, construction site roads, ramps, demolition areas)
  • Height clearances at lines, signals, tunnels as well as contact with utilities for temporary lifting/shutdowns
  • Weather and visibility influences (rain, wind, ice) with effects on braking distance and load securing

Regulatory conditions and escort

Oversize and heavy transports often receive special permits with conditions: escort vehicles, safety personnel, temporary closures, defined driving time windows, or speed limits are common. In practice, a robust schedule and communication concept that also provides for alternative routes is recommended. Legal requirements must always be clarified on a project-specific basis; binding statements are issued solely by the competent authorities.

Vehicle and technology overview

The choice of transport equipment depends on mass, dimensions, center of gravity, and the required interface on the construction site. With pre-segmented concrete elements from the use of concrete pulverizers or split rock blocks from natural stone extraction, height and width are often reduced – with positive effects on the transport class and the scope of permits.

Low-bed and deck-low trailers

Low-bed and semi-low loaders are universal carriers for construction and deconstruction equipment: hydraulic power units, combination shears, multi cutters, and rock splitting cylinders can be transported with low loading heights and adaptable running gear. For heavy concrete or steel segments produced with concrete pulverizers, steel shears, or tank cutters, deep load decks offer advantages for clearance height and center of gravity.

Modular axle lines and SPMT

Modular axle lines enable finely graduated axle load distribution and are useful for extreme loads or irregular geometries. Self-propelled modular transporters (SPMT) are used when loads have to be positioned with millimeter precision in confined spaces, for example for heavy machine foundations, massive concrete blocks from special deconstruction, or large natural stone monoliths from extraction.

Load securing and stability

Load securing ensures the stability of the cargo and prevents relative movements. A distinction is mainly made between tie-down lashing (frictional securing) and direct lashing (positive locking). The basis is provided by friction coefficients, lashing angles, pretensioning forces, and the quality of the lashing points. Anti-slip mats, edge protectors, and positive-fitting supports are essential for hard and sharp-edged loads such as split concrete or rock parts.

  1. Plan load pickup: determine dimensions, mass, center of gravity, and lifting points
  2. Prepare bedding and support surfaces: distribute loads, increase friction, protect edges
  3. Select securing method: prefer direct lashing for irregular shapes, tie-down lashing only with sufficient friction
  4. Size lashing equipment: document quantity, grade, angles, and pretension
  5. Control: re-check after the first kilometers and after roadway events (braking, evasive maneuvers)

Specifics for concrete and rock

Pre-segmented components from concrete pulverizers, combinations of concrete pulverizer and steel shear, or split stone blocks often have irregular support surfaces. To minimize notch stresses, high-compressive intermediate layers are used. Cracks and spalling must be anticipated; a securing concept with additional retention systems (e.g., nets or side boards) can be sensible. When handling heavy blocks from natural stone extraction, a stable center of gravity is more important than absolute positive locking – the bedding must be designed to be tilt-stable.

Interfaces to on-site operations

Transport does not end at the construction site access. Handovers to cranes, lifting systems, or mobile handling equipment as well as organization of the last meters are crucial. In the application areas of concrete demolition and special deconstruction, strip-out and cutting, rock excavation and tunnel construction, natural stone extraction, and special missions, the interlocking of transport, lifting, and separation technology is decisive for progress.

Reducing mass and dimensions through pre-segmentation

By using concrete pulverizers and rock and concrete splitters in a targeted manner, components can be prepared so that height and width become transport-friendly. Combination shears, multi cutters, and steel shears cut reinforcement and steel beams, tank cutters segment vessels. The result is transportable units that often require lower transport classes, allow better axle load distributions, and can reduce the number of trips – always depending on structural analysis, material, and the site concept.

Risks, safety, and environmental aspects

Heavy haulage requires a coordinated safety concept: traffic safeguarding, communication between driving and safety personnel, emergency plans, and clear responsibilities are indispensable. Environmental aspects such as noise, vibration, and emissions are mitigated through suitable time windows, route selection, and driving style. When transporting concrete or rock material, dust and dirt ingress must be avoided; coverings and cleaning the roadways at entrances and exits are part of good practice. Requirements from authorities and occupational safety must be observed; specific measures must always be defined on a project basis.

Key figures and documentation

Weighing logs, surveys, lashing and lifting plans, route approvals, and inspection reports serve quality assurance. Digital tools such as telematics, load distribution calculators, and surveying systems support planning. For complex transports, a written method statement with checklists is recommended, from the arrival of vehicles to loading and unloading – including condition documentation of the cargo, for example for sensitive concrete components or precisely cut steel segments.

Practical examples from the application areas

Requirements differ between industries, yet principles repeat. Some typical constellations show the interlocking of separation and transport technology:

  • Concrete demolition and special deconstruction: Pre-segmented bridge spans are brought into transportable units using concrete pulverizers and steel shears; deep load decks reduce clearance heights, direct lashing secures irregular geometries.
  • Strip-out and cutting: Steel beams, stairwells, and equipment frames are separated with combination shears and multi cutters; short, heavy pieces facilitate axle load distribution and reduce maneuvering times in tight inner-city areas.
  • Rock excavation and tunnel construction: Blocks released with rock and concrete splitters are loaded onto modular axle lines; focus on tilt-stable bedding and low center of gravity for gradients and hairpins.
  • Natural stone extraction: Raw blocks from the quarry are bedded with positive fit, edges protected, and transported with low build-up height to use the route height efficiently.
  • Special mission: Tank cutters segment large vessels; the resulting segments are arranged so that cut edges are protected and the bearing surfaces introduce loads evenly.

Typical mistakes and how to avoid them

Errors in haulage logistics have a direct impact on safety, schedule, and costs. The most common causes can be avoided through structured preparation:

  • Unclear mass and center-of-gravity data: weigh, measure, and document before loading
  • Insufficient bedding: plan compressive intermediate layers and defined bearing points
  • Wrong securing method: prefer direct lashing for irregular components, protect edges
  • Unchecked route bottlenecks: clarify drive-through feasibility and height clearances in advance, keep an alternative route ready
  • Communication gaps: fix loading and driving instructions in writing, define responsibilities
  • Neglected handovers: coordinate crane and lifting plans with transport planning, avoid waiting times