{"id":19907,"date":"2025-12-31T16:46:07","date_gmt":"2025-12-31T15:46:07","guid":{"rendered":"https:\/\/www.darda.de\/?page_id=19907"},"modified":"2026-05-29T12:17:02","modified_gmt":"2026-05-29T10:17:02","slug":"tunnel-heading","status":"publish","type":"page","link":"https:\/\/www.darda.de\/en\/knowledge\/tunnel-heading","title":{"rendered":"Tunnel heading"},"content":{"rendered":"<div class=\"wissen-inhaltsbereich\">\n<p><em>Tunnel heading<\/em> describes the step-by-step creation of underground cavities with typically small to medium cross-sections. It is used in classic adit construction, in tunnel construction for cross passages and escape routes, in utility and cable works, and in mining. Rock or concrete is removed in controlled work cycles; the tunnel face is secured, the cross-section is profiled, and the lining is installed. In this technical environment, hydraulic tools are often used that operate with low vibration levels and deliver precise results in confined conditions. These include, in Darda GmbH\u2019s portfolio in particular, <a href=\"https:\/\/www.darda.de\/en\/product-overview\/hydraulic-rock-and-concrete-splitters\">rock and concrete splitters<\/a>, <strong>concrete demolition shears<\/strong>, hydraulic power packs, combination shears, rock wedge splitters, Multi Cutters, steel shears, and tank cutters. The approach is selected where flexible advance, low emissions, and precise geometry are critical under spatial or regulatory constraints.<\/p>\n<h2>Definition: What is meant by tunnel heading?<\/h2>\n<p>Tunnel heading refers to the creation of an underground cavity (adit) by stepwise excavation at the tunnel face followed by immediate support and lining. Typical features are smaller to medium cross-sections, closed boundary conditions, and varying geology. Depending on the ground, the heading proceeds mechanically (excavator with suitable excavator attachments, partial-face cutting, drilling and splitting), by drilling and blasting, or using special methods. In contrast to machine full-face excavation of entire tunnel cross-sections (e.g., with tunnel boring machines), tunnel heading is more flexible, allows adaptations to the geology, and is frequently used for exploration headings, cable and utility headings, cross passages, connection and escape headings, as well as access structures. In some contexts, the advance is also referred to as a drift or adit advance; short rounds with immediate measurements enable adaptive control of support and lining.<\/p>\n<h2>Methods and construction sequence in heading works<\/h2>\n<p>The construction sequence is divided into short advance cycles: excavation at the tunnel face, trimming and profiling, support and lining, material haulage, and construction logistics. The choice of method depends on rock mass, hydrogeology, cross-section, surrounding conditions, and protected assets at the surface. Continuous monitoring in line with the observational method informs adjustments to round length, support classes, and logistics.<\/p>\n<h3>Excavation techniques<\/h3>\n<ul>\n<li>Mechanical heading: Loosening by excavator with suitable excavator attachments, partial-face cutting, drilling, wedging, and hydraulic splitting. Here, <strong>rock and concrete splitters<\/strong> and rock wedge splitters are used to open rock in a controlled manner without generating relevant vibrations.<\/li>\n<li>Drilling and blasting: Classic cycle of drill plan, charging, blasting, ventilation, and mucking. In sensitive areas, explosive energy is reduced and combined with splitting technology to minimize vibrations.<\/li>\n<li>Selective removal: Trimming, profile correction, and exposing structures with concrete demolition shears, Multi Cutters, or combination shears &#8211; especially when dismantling existing underground structures.<\/li>\n<li>Kerf pre-cutting and slot drilling: Targeted slots or relief holes at the face create preferential break lines, improve profile accuracy, and reduce overbreak in heterogeneous ground.<\/li>\n<\/ul>\n<h3>Support and lining<\/h3>\n<ul>\n<li>Initial support: Shotcrete, anchors, lattice girder beams, and spiling umbrellas to stabilize the rock mass immediately after each round.<\/li>\n<li>Final lining: Shotcrete shell, masonry lining, or segment ring-like solutions for special requirements; profile accuracy is checked regularly.<\/li>\n<li>Construction-phase profiling: <strong>concrete demolition shears<\/strong> and Multi Cutters are used to remove reinforced concrete in a controlled way, release built-in components, and expose reinforcement.<\/li>\n<li>Waterproofing and drainage interfaces: Controlled transitions between temporary support, drainage layers, and permanent waterproofing reduce leakage risks and facilitate durable finishing.<\/li>\n<li>Monitoring and control measurements: Convergence, shotcrete thickness checks, and anchor pull-out tests verify the effectiveness of support measures.<\/li>\n<\/ul>\n<h3>Material haulage logistics<\/h3>\n<p>Depending on heading length and gradient, haulage is via haulage vehicles, conveyor belts, or rails. Hydraulic power packs supply the attachments and handheld tools with the required energy, even in areas with limited power supply or restrictive emission requirements. Ventilation staging, dust extraction, and clear traffic management plans are coordinated with haulage to maintain safe visibility and air quality.<\/p>\n<h2>Applications of tunnel heading and links to tools<\/h2>\n<p>Tunnel heading serves as a precise and adaptable method in numerous disciplines. Tool selection is always project-specific.<\/p>\n<ul>\n<li>Rock excavation and tunnel construction: Controlled removal of hard rock with splitters; rework of edges, niches, and profiles with Multi Cutters. Under delicate tunnel face conditions, splitting techniques can complement the drilling and blasting sequence.<\/li>\n<li>Concrete demolition and special demolition: Removal of reinforcements, transverse openings, and temporary construction states with <strong>concrete demolition shears<\/strong>, steel shears, and combination shears; exposing and cutting reinforcement.<\/li>\n<li>Strip-out and cutting: In existing underground structures, embedded parts, steel sections, pipelines, and tanks are cut with steel shears, combination shears, or tank cutters &#8211; especially during conversions and connection works.<\/li>\n<li>Natural stone extraction: Splitting and loosening of rock beds in underground extraction with rock wedge splitters; low vibration levels protect sensitive surroundings.<\/li>\n<li>Special applications: Work in hospital environments, heritage areas, or densely built urban settings requires low-emission, low-vibration methods. Hydraulic splitters and concrete demolition shears help meet the requirements.<\/li>\n<li>Interfaces to shafts and breakthroughs: Accurate opening-up, enlargement, and connection works at shafts, caverns, and breakthroughs benefit from low-vibration, profile-true techniques.<\/li>\n<\/ul>\n<h2>Geotechnics, investigation, and planning<\/h2>\n<p>Robust planning is based on ground investigation, laboratory testing, hydrogeological analyses, and forecasts of rock mass behavior. From this derive the heading method, round length, support concept, water control, and emergency strategies. A geotechnical baseline and trigger values for the observational method ensure that measurements translate directly into predefined actions and contingency measures.<\/p>\n<h3>Influencing factors for method selection<\/h3>\n<ol>\n<li>Strength, bedding, and jointing of the rock mass<\/li>\n<li>Water inflows, gas occurrences, and rock pressure<\/li>\n<li>Overburden, proximity to structures, and permissible vibrations<\/li>\n<li>Cross-section geometry, radii of curvature, and accessibility<\/li>\n<li>Occupational safety, escape routes, ventilation, and logistics<\/li>\n<\/ol>\n<p>Where strict vibration and noise limits apply, mechanical removal, <strong>rock and concrete splitters<\/strong> and <strong>concrete demolition shears<\/strong> are preferred to loosen the tunnel face in a controlled manner and ensure profile accuracy. This supports compliance with permit conditions and the protection of adjacent structures and infrastructure.<\/p>\n<h2>Safety and health protection in tunnel heading<\/h2>\n<p>Safety takes priority. Underground works require regulated workflows, training, personal protective equipment, effective ventilation, fire protection and explosion protection, and orderly material handling. The handling of explosives, the cutting of steel components, and hydraulic splitting must be planned and supervised in accordance with applicable regulations. The statements are of a general nature; project-specific requirements of the authorities and the relevant codes are decisive. Lockout-tagout procedures for hydraulic power packs, routine hose and coupling inspections, and regular emergency drills are integral to safe operations.<\/p>\n<h3>Emissions and vibrations<\/h3>\n<p>Dust, vibrations, and noise must be minimized. Hydraulic splitting technology operates with low vibration levels, which reduces settlement and impacts on structures. <strong>Concrete demolition shears<\/strong> and steel shears enable controlled separation of reinforced components, lines, or profiles with low emissions.<\/p>\n<ul>\n<li>Dust control: Wet drilling, misting, and local extraction at the face reduce airborne particles.<\/li>\n<li>Vibration management: Short rounds, pre-splitting, and careful charge design limit ground-borne vibrations.<\/li>\n<li>Noise mitigation: Silenced power units, acoustic screens, and optimized shift planning reduce exposure.<\/li>\n<\/ul>\n<h2>Materials, lining types, and finishing<\/h2>\n<p>Initial and final linings range from shotcrete with anchors to masonry linings. During adjustments, temporary supports are removed, edges are re-profiled, and embedded components are relocated. Where required, waterproofing membranes, waterstops, and drainage layers are integrated with tight control of surface preparation and bonding conditions.<\/p>\n<ul>\n<li>Profile correction: Trimming with splitters, fine finishing with Multi Cutters.<\/li>\n<li>Dismantling of temporary elements: Removing spiles, lattice girder beams, and auxiliary structures with <strong>concrete demolition shears<\/strong> and steel shears.<\/li>\n<li>Steel and tank works: Cutting steel beams or underground tanks with tank cutters within defined safety concepts.<\/li>\n<li>Waterproofing connections and penetration details: Careful trimming and cleaning to ensure reliable bonding and watertightness around anchors, ducts, and inserts.<\/li>\n<\/ul>\n<h2>Construction logistics and power supply<\/h2>\n<p>In headings, cross-section and airflow limit the choice of equipment. Compact hydraulic power packs supply splitters, shears, and cutters via hose lines. Low waste heat, demand-based power, and safe quick couplings are important. Transport routes, intermediate storage, and maintenance areas must be planned so that heading and support proceed without interfering with each other. Energy management, ventilation capacity, and safe turning bays are coordinated with shift and traffic concepts.<\/p>\n<ul>\n<li>Segregation of personnel and plant routes reduces conflicts and waiting times.<\/li>\n<li>Buffer zones for materials and muck bins stabilize cycle times and minimize double handling.<\/li>\n<li>Redundant power and ventilation, plus clear evacuation paths, increase resilience in incident scenarios.<\/li>\n<\/ul>\n<h2>Typical challenges and technical solutions<\/h2>\n<ul>\n<li>Blocky or anisotropic rock mass: Preferably drilling and splitting along existing joints; reduced explosive charges to preserve the tunnel face.<\/li>\n<li>Water inflows: Pre-injection, drainage, and secured material haulage; corrosion-protected tools and regular maintenance.<\/li>\n<li>Reinforced concrete in existing structures: Selective deconstruction with <strong>concrete demolition shears<\/strong>, exposing reinforcement, then cutting with steel shears.<\/li>\n<li>Proximity to sensitive structures: Low-vibration sequences, short rounds, splitters instead of heavy percussion hammers.<\/li>\n<li>Confined geometries: Compact handheld tools and modular power packs to ensure reach and maneuverability.<\/li>\n<li>Variable ground classes along the alignment: Maintain the option to switch between mechanical splitting, drilling and blasting, and partial-face cutting.<\/li>\n<li>Heat load and limited ventilation: Stage exhaust and intake, plan duty cycles, and prefer low-emission hydraulic equipment.<\/li>\n<\/ul>\n<h2>Application examples in the project workflow<\/h2>\n<h3>Exploration and access headings<\/h3>\n<p>Small cross-sections are advanced for geology and groundwater investigation. Mechanical removal and splitting limit vibrations; profile correction is performed with Multi Cutters. Data and observations from the face feed back into risk assessment, design updates, and support optimization.<\/p>\n<h3>Cross passages and escape tunnels<\/h3>\n<p>Precise breakthroughs are required in existing tunnel bores. <strong>Concrete demolition shears<\/strong> create controlled openings; steel shears cut reinforcement and embedded components. Survey-controlled alignment, defined stand-off distances, and staged support ensure safe, accurate breakthroughs.<\/p>\n<h3>Rehabilitation and special demolition<\/h3>\n<p>When removing old linings, concrete is released in sections, steel is cut, and the profile is re-established. <strong>rock and concrete splitters<\/strong> minimize impacts on the surroundings. Sequenced deconstruction with intermediate stabilization maintains serviceability of adjacent structures and minimizes downtime.<\/p>\n<h2>Sustainability, resource efficiency, and quality<\/h2>\n<p>Resource conservation starts with method selection: lower vibrations, minimized energy input, and clean, source-separated handling of muck. Hydraulic tools with demand-based power reduce emissions. Quality assurance includes measurements of profile accuracy, documentation of support elements, visual inspections of the tunnel face, and regular functional tests of the equipment. Recycling of steel and concrete, beneficial reuse of excavated material where feasible, and energy monitoring support sustainability targets; lifecycle-oriented documentation strengthens long-term durability.<\/p>\n<h2>Terms and classification in the context of tunnel construction<\/h2>\n<p>Tunnel heading lies between classic adit construction and large cross-section tunnel excavation. Adits serve as exploration, service, cable, or water headings, as cross passages between bores, and as access to caverns. Shafts connect the surface and headings; cross passages create transverse connections. In all cases, the principles of safe excavation, timely support, and profile-accurate execution apply &#8211; supported by suitable hydraulic tools such as <strong>concrete demolition shears<\/strong> and <strong>rock and concrete splitters<\/strong>. Unlike full-face machine excavation, heading relies on modular equipment and staged cycles that can be paused, inspected, and adapted to local conditions.<\/p>\n<\/div>\n","protected":false},"excerpt":{"rendered":"<p>Tunnel heading describes the step-by-step creation of underground cavities with typically small to medium cross-sections. It is used in classic adit construction, in tunnel construction for cross passages and escape routes, in utility and cable works, and in mining. Rock or concrete is removed in controlled work cycles; the tunnel <a class=\"moretag\" href=\"https:\/\/www.darda.de\/en\/knowledge\/tunnel-heading\">read more&#8230;<\/a><\/p>\n","protected":false},"author":9,"featured_media":0,"parent":14846,"menu_order":0,"comment_status":"open","ping_status":"open","template":"tmpl\/template-wissen.php","meta":{"_acf_changed":false,"footnotes":"","_members_access_role":[],"_members_access_error":""},"class_list":["post-19907","page","type-page","status-publish","hentry"],"acf":[],"yoast_head":"<!-- This site is optimized with the Yoast SEO plugin v28.5 - https:\/\/yoast.com\/product\/yoast-seo-wordpress\/ -->\n<title>Tunnel Heading - Underground Excavation Method<\/title>\n<meta name=\"description\" content=\"Explore tunnel heading for underground excavation \u25b7 method, steps, support &amp; low vibration for precise, safe results.\" \/>\n<meta name=\"robots\" content=\"index, follow, max-snippet:-1, max-image-preview:large, max-video-preview:-1\" \/>\n<link rel=\"canonical\" href=\"https:\/\/www.darda.de\/en\/knowledge\/tunnel-heading\" \/>\n<meta property=\"og:locale\" content=\"en_US\" \/>\n<meta property=\"og:type\" content=\"article\" \/>\n<meta property=\"og:title\" content=\"Tunnel Heading - Underground Excavation Method\" \/>\n<meta property=\"og:description\" content=\"Explore tunnel heading for underground excavation \u25b7 method, steps, support &amp; low vibration for precise, safe results.\" \/>\n<meta property=\"og:url\" content=\"https:\/\/www.darda.de\/en\/knowledge\/tunnel-heading\" \/>\n<meta property=\"og:site_name\" content=\"Darda GmbH\" \/>\n<meta property=\"article:publisher\" content=\"https:\/\/www.facebook.com\/DardaDemolition\" \/>\n<meta property=\"article:modified_time\" content=\"2026-05-29T10:17:02+00:00\" \/>\n<meta name=\"twitter:card\" content=\"summary_large_image\" \/>\n<meta name=\"twitter:label1\" content=\"Est. reading time\" \/>\n\t<meta name=\"twitter:data1\" content=\"9 minutes\" \/>\n<script type=\"application\/ld+json\" class=\"yoast-schema-graph\">{\"@context\":\"https:\\\/\\\/schema.org\",\"@graph\":[{\"@type\":\"WebPage\",\"@id\":\"https:\\\/\\\/www.darda.de\\\/en\\\/knowledge\\\/tunnel-heading\",\"url\":\"https:\\\/\\\/www.darda.de\\\/en\\\/knowledge\\\/tunnel-heading\",\"name\":\"Tunnel Heading - Underground Excavation Method\",\"isPartOf\":{\"@id\":\"https:\\\/\\\/www.darda.de\\\/en#website\"},\"datePublished\":\"2025-12-31T15:46:07+00:00\",\"dateModified\":\"2026-05-29T10:17:02+00:00\",\"description\":\"Explore tunnel heading for underground excavation \u25b7 method, steps, support & low vibration for precise, safe results.\",\"breadcrumb\":{\"@id\":\"https:\\\/\\\/www.darda.de\\\/en\\\/knowledge\\\/tunnel-heading#breadcrumb\"},\"inLanguage\":\"en-US\",\"potentialAction\":[{\"@type\":\"ReadAction\",\"target\":[\"https:\\\/\\\/www.darda.de\\\/en\\\/knowledge\\\/tunnel-heading\"]}]},{\"@type\":\"BreadcrumbList\",\"@id\":\"https:\\\/\\\/www.darda.de\\\/en\\\/knowledge\\\/tunnel-heading#breadcrumb\",\"itemListElement\":[{\"@type\":\"ListItem\",\"position\":1,\"name\":\"Home\",\"item\":\"https:\\\/\\\/www.darda.de\\\/en\"},{\"@type\":\"ListItem\",\"position\":2,\"name\":\"Knowledge\",\"item\":\"https:\\\/\\\/www.darda.de\\\/en\\\/knowledge\"},{\"@type\":\"ListItem\",\"position\":3,\"name\":\"Tunnel heading\"}]},{\"@type\":\"WebSite\",\"@id\":\"https:\\\/\\\/www.darda.de\\\/en#website\",\"url\":\"https:\\\/\\\/www.darda.de\\\/en\",\"name\":\"Darda GmbH\",\"description\":\"\",\"publisher\":{\"@id\":\"https:\\\/\\\/www.darda.de\\\/en#organization\"},\"alternateName\":\"Abbruchwerkzeuge\",\"potentialAction\":[{\"@type\":\"SearchAction\",\"target\":{\"@type\":\"EntryPoint\",\"urlTemplate\":\"https:\\\/\\\/www.darda.de\\\/en?s={search_term_string}\"},\"query-input\":{\"@type\":\"PropertyValueSpecification\",\"valueRequired\":true,\"valueName\":\"search_term_string\"}}],\"inLanguage\":\"en-US\"},{\"@type\":\"Organization\",\"@id\":\"https:\\\/\\\/www.darda.de\\\/en#organization\",\"name\":\"Darda GmbH\",\"url\":\"https:\\\/\\\/www.darda.de\\\/en\",\"logo\":{\"@type\":\"ImageObject\",\"inLanguage\":\"en-US\",\"@id\":\"https:\\\/\\\/www.darda.de\\\/en#\\\/schema\\\/logo\\\/image\\\/\",\"url\":\"https:\\\/\\\/www.darda.de\\\/wp-content\\\/uploads\\\/2017\\\/09\\\/android-icon-192x192-1.png\",\"contentUrl\":\"https:\\\/\\\/www.darda.de\\\/wp-content\\\/uploads\\\/2017\\\/09\\\/android-icon-192x192-1.png\",\"width\":192,\"height\":192,\"caption\":\"Darda GmbH\"},\"image\":{\"@id\":\"https:\\\/\\\/www.darda.de\\\/en#\\\/schema\\\/logo\\\/image\\\/\"},\"sameAs\":[\"https:\\\/\\\/www.facebook.com\\\/DardaDemolition\",\"https:\\\/\\\/www.instagram.com\\\/darda_demolition\",\"https:\\\/\\\/www.youtube.com\\\/user\\\/DardaGmbH\",\"https:\\\/\\\/www.xing.com\\\/pages\\\/darda-gmbh\",\"https:\\\/\\\/de.linkedin.com\\\/company\\\/darda-gmbh\"]}]}<\/script>\n<!-- \/ Yoast SEO plugin. -->","yoast_head_json":{"title":"Tunnel Heading - Underground Excavation Method","description":"Explore tunnel heading for underground excavation \u25b7 method, steps, support & low vibration for precise, safe results.","robots":{"index":"index","follow":"follow","max-snippet":"max-snippet:-1","max-image-preview":"max-image-preview:large","max-video-preview":"max-video-preview:-1"},"canonical":"https:\/\/www.darda.de\/en\/knowledge\/tunnel-heading","og_locale":"en_US","og_type":"article","og_title":"Tunnel Heading - Underground Excavation Method","og_description":"Explore tunnel heading for underground excavation \u25b7 method, steps, support & low vibration for precise, safe results.","og_url":"https:\/\/www.darda.de\/en\/knowledge\/tunnel-heading","og_site_name":"Darda GmbH","article_publisher":"https:\/\/www.facebook.com\/DardaDemolition","article_modified_time":"2026-05-29T10:17:02+00:00","twitter_card":"summary_large_image","twitter_misc":{"Est. reading time":"9 minutes"},"schema":{"@context":"https:\/\/schema.org","@graph":[{"@type":"WebPage","@id":"https:\/\/www.darda.de\/en\/knowledge\/tunnel-heading","url":"https:\/\/www.darda.de\/en\/knowledge\/tunnel-heading","name":"Tunnel Heading - Underground Excavation Method","isPartOf":{"@id":"https:\/\/www.darda.de\/en#website"},"datePublished":"2025-12-31T15:46:07+00:00","dateModified":"2026-05-29T10:17:02+00:00","description":"Explore tunnel heading for underground excavation \u25b7 method, steps, support & low vibration for precise, safe results.","breadcrumb":{"@id":"https:\/\/www.darda.de\/en\/knowledge\/tunnel-heading#breadcrumb"},"inLanguage":"en-US","potentialAction":[{"@type":"ReadAction","target":["https:\/\/www.darda.de\/en\/knowledge\/tunnel-heading"]}]},{"@type":"BreadcrumbList","@id":"https:\/\/www.darda.de\/en\/knowledge\/tunnel-heading#breadcrumb","itemListElement":[{"@type":"ListItem","position":1,"name":"Home","item":"https:\/\/www.darda.de\/en"},{"@type":"ListItem","position":2,"name":"Knowledge","item":"https:\/\/www.darda.de\/en\/knowledge"},{"@type":"ListItem","position":3,"name":"Tunnel heading"}]},{"@type":"WebSite","@id":"https:\/\/www.darda.de\/en#website","url":"https:\/\/www.darda.de\/en","name":"Darda GmbH","description":"","publisher":{"@id":"https:\/\/www.darda.de\/en#organization"},"alternateName":"Abbruchwerkzeuge","potentialAction":[{"@type":"SearchAction","target":{"@type":"EntryPoint","urlTemplate":"https:\/\/www.darda.de\/en?s={search_term_string}"},"query-input":{"@type":"PropertyValueSpecification","valueRequired":true,"valueName":"search_term_string"}}],"inLanguage":"en-US"},{"@type":"Organization","@id":"https:\/\/www.darda.de\/en#organization","name":"Darda GmbH","url":"https:\/\/www.darda.de\/en","logo":{"@type":"ImageObject","inLanguage":"en-US","@id":"https:\/\/www.darda.de\/en#\/schema\/logo\/image\/","url":"https:\/\/www.darda.de\/wp-content\/uploads\/2017\/09\/android-icon-192x192-1.png","contentUrl":"https:\/\/www.darda.de\/wp-content\/uploads\/2017\/09\/android-icon-192x192-1.png","width":192,"height":192,"caption":"Darda GmbH"},"image":{"@id":"https:\/\/www.darda.de\/en#\/schema\/logo\/image\/"},"sameAs":["https:\/\/www.facebook.com\/DardaDemolition","https:\/\/www.instagram.com\/darda_demolition","https:\/\/www.youtube.com\/user\/DardaGmbH","https:\/\/www.xing.com\/pages\/darda-gmbh","https:\/\/de.linkedin.com\/company\/darda-gmbh"]}]}},"_links":{"self":[{"href":"https:\/\/www.darda.de\/en\/wp-json\/wp\/v2\/pages\/19907","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/www.darda.de\/en\/wp-json\/wp\/v2\/pages"}],"about":[{"href":"https:\/\/www.darda.de\/en\/wp-json\/wp\/v2\/types\/page"}],"author":[{"embeddable":true,"href":"https:\/\/www.darda.de\/en\/wp-json\/wp\/v2\/users\/9"}],"replies":[{"embeddable":true,"href":"https:\/\/www.darda.de\/en\/wp-json\/wp\/v2\/comments?post=19907"}],"version-history":[{"count":2,"href":"https:\/\/www.darda.de\/en\/wp-json\/wp\/v2\/pages\/19907\/revisions"}],"predecessor-version":[{"id":27887,"href":"https:\/\/www.darda.de\/en\/wp-json\/wp\/v2\/pages\/19907\/revisions\/27887"}],"up":[{"embeddable":true,"href":"https:\/\/www.darda.de\/en\/wp-json\/wp\/v2\/pages\/14846"}],"wp:attachment":[{"href":"https:\/\/www.darda.de\/en\/wp-json\/wp\/v2\/media?parent=19907"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}