{"id":19712,"date":"2025-12-10T14:18:26","date_gmt":"2025-12-10T13:18:26","guid":{"rendered":"https:\/\/www.darda.de\/?page_id=19712"},"modified":"2026-05-15T11:34:03","modified_gmt":"2026-05-15T09:34:03","slug":"formwork-plan","status":"publish","type":"page","link":"https:\/\/www.darda.de\/en\/knowledge\/formwork-plan","title":{"rendered":"Formwork plan"},"content":{"rendered":"<div class=\"wissen-inhaltsbereich\">\n<p>A formwork plan is the central working basis for concrete placement in building and civil engineering. It translates structural and architectural requirements into an executable solution made of formwork sheathing, formwork scaffold, anchors, props, and work sequences. Precisely planned formwork shortens construction times, secures the required surface quality, and minimizes rework. Where dimensional corrections, openings, or the removal of defects are still required, construction companies often use low-vibration methods as part of concrete demolition and special demolition-for example, concrete demolition shears or controlled splitting with <a href=\"https:\/\/www.darda.de\/en\/product-overview\/hydraulic-rock-and-concrete-splitters\">rock and concrete splitters<\/a>, powered by <a href=\"https:\/\/www.darda.de\/en\/product-overview\/hydraulic-power-units\">suitable hydraulic power units<\/a>. This preserves the existing structure and maintains the durability of adjacent structural elements. In practice, the formwork plan also serves as the coordinated shop drawing for shuttering and falsework, aligning pour breaks, logistics, and inspection points.<\/p>\n<h2>Definition: What is meant by a formwork plan?<\/h2>\n<p>A formwork plan is a set of drawings and calculation data that governs the production of a concrete member using a temporary mold-the formwork. It contains geometry, layer build-up of the formwork sheathing, spans and prop spacings, anchor and joint grids, concrete placement sections, permissible fresh concrete pressures, assembly and dismantling sequence, as well as notes on occupational safety. In contrast to the reinforcement plan, the formwork plan describes the shaping and load-bearing auxiliary structure and its actions during concreting. It may include 2D and 3D elements and is often linked with the formwork structural analysis, the work schedule, and approval protocols.<\/p>\n<p><em>Outcome and purpose:<\/em> The formwork plan defines what is to be built, with which system, in what sequence, and under which boundary conditions. It forms the basis for <strong>cost, quality, and time<\/strong> control during the concrete pour.<\/p>\n<h2>Structure and contents of a formwork plan<\/h2>\n<p>The content depends on the member, construction method, and fair-faced concrete requirements. For safe and economical execution, at least the following information is required:<\/p>\n<ul>\n<li>Member geometry with axes, elevations, formwork sheathing thickness, and joint layout; identification of fair-faced concrete areas<\/li>\n<li>Formwork system, formwork sheathing material, and permissible loads, including permissible <em>fresh concrete pressures<\/em> and placing rates<\/li>\n<li>Load-bearing structure: props, yoke beam girders, cross beams, shoring towers and their spacings, bearings, and subgrade requirements<\/li>\n<li>Anchor points, anchor spacing, anchor forces, edge distances, and blockouts for anchors<\/li>\n<li>Concrete placement sections, sequencing, construction joints, start and end areas<\/li>\n<li>Blockouts, embedded items, penetrations (MEP, fixings) with tolerances<\/li>\n<li>Assembly and stripping notes, stripping times, and protection against early damage<\/li>\n<li>Quality targets: surface classes, edge detailing, fair-faced concrete matrix, cleaning and release agent notes<\/li>\n<li>Inspections, approvals, inspection intervals, and documentation of dimensional accuracy<\/li>\n<\/ul>\n<p>Depending on element type (walls, slabs, columns, beams), the plan specifies <strong>reference grids and survey benchmarks<\/strong>, reservoir or overfill allowances, and <em>tolerance classes<\/em>. Where required, curing concepts, pre-assembly measures, and reuse strategies for sheathing are documented to stabilize quality across cycles.<\/p>\n<h3>Load assumptions and fresh concrete pressure<\/h3>\n<p>The design is based on fresh concrete pressure development, self-weight and additional loads (e.g., placement rate, temperature, concrete composition), wind, and assembly loads. The placing rate must be selected so that permissible formwork pressures are not exceeded. Standards and codes are to be observed project-specifically; specific limit values and verifications are to be provided by qualified professionals. For concretes with different rheology (e.g., SCC versus vibrated mixes), pressure development and rate control differ and must be reflected in the verification and stated as binding execution parameters.<\/p>\n<h3>Surface requirements and joints<\/h3>\n<p>For fair-faced concrete, the formwork sheathing, joint grid, and anchor pattern are defined early. Uniform sheathing qualities, clean transitions, and clearly defined construction joints prevent rework. If ridges, spalls, or honeycombs nevertheless occur, the defective concrete is first removed to a sound core; for precise edge corrections, concrete demolition shears are often used. Release agents must be compatible with the sheathing and the target surface class, with application quantity and intervals specified to secure repeatability.<\/p>\n<ul>\n<li>Align seams and tie rows to architectural grids to avoid visual noise<\/li>\n<li>Orient plywood and panel texture consistently to control reflectivity and patterning<\/li>\n<\/ul>\n<h2>Creation: From preliminary design to work instructions<\/h2>\n<ol>\n<li>Document review: structural analysis, reinforcement plans, architectural plans, construction stages, subsoil<\/li>\n<li>Concept selection: formwork system, sequencing, concrete logistics, crane and lifting device<\/li>\n<li>Pre-design of the load-bearing structure, definition of anchor spacing and prop spans<\/li>\n<li>Preparation of drawings including bills of materials and assembly sequence<\/li>\n<li>Coordination with execution, reinforcement, and MEP; resolve clashes<\/li>\n<li>Approval processes and-where required-verifiable calculations<\/li>\n<li>Site briefing, checklists, visual inspections, and documentation<\/li>\n<\/ol>\n<p><em>Typical deliverables:<\/em><\/p>\n<ul>\n<li>Formwork layout drawings with pour breaks, anchor patterns, and tie-in details<\/li>\n<li>Parts lists for panels, beams, props, anchors, and accessories including reuse notes<\/li>\n<li>Method statement excerpts defining placing rate, vibration method, stripping criteria, and curing<\/li>\n<\/ul>\n<h2>Interfaces with reinforcement, MEP, and openings<\/h2>\n<p>Most deviations during execution arise at penetrations, blockouts, and embedded items. A good formwork plan visualizes these interfaces and defines tolerance windows. If openings in concrete are later enlarged or newly created, for example during building gutting and cutting, low-vibration methods should be used. In practice, the combination of pre-drilling, controlled splitting with <strong>hydraulic wedge splitters<\/strong>, and precise removal with <strong>concrete demolition shears<\/strong>, driven by suitable hydraulic power packs, has proven effective. This allows service shafts, door openings, or niches to be produced to size without damaging adjacent components.<\/p>\n<ul>\n<li>Breakthroughs: clearly define location, size, reinforcement routing, and edge protection in the plan<\/li>\n<li>Embedded items: formwork anchors, brackets, anchor channels-observe anchorage and watertightness<\/li>\n<li>Stripping aids: release agents, negative forms, retention systems for damage-free removal<\/li>\n<li>Set out control: survey points and permissible deviation envelopes for penetrations and sleeves<\/li>\n<li>As-built records: mark and document final positions for future maintenance and conversions<\/li>\n<\/ul>\n<h2>Quality assurance, tolerances, and documentation<\/h2>\n<p>To ensure dimensional accuracy, anchor spacing, prop spans, plumb faces, bearings, and protective measures are checked before concreting. After stripping, visual and dimensional inspection takes place, documented by measurement logs and photo documentation. Typical defects include honeycombs, voids, ridge formation, and edge spalling. Proper rework includes:<\/p>\n<ul>\n<li>Removing loose or damaged zones down to sound concrete, for example with concrete demolition shears<\/li>\n<li>Local, low-vibration splitting of larger defective concrete areas using hydraulic wedge splitters<\/li>\n<li>Reprofiling, fine finishing, and curing in accordance with technical data sheets<\/li>\n<\/ul>\n<p>Inspection criteria should reference project-specific tolerances and acceptance classes. Measuring equipment, calibration status, and sampling frequencies are to be stated. Non-conformities are processed with defined corrective and preventive actions, including adjustments to placing rate or temporary bracing where required.<\/p>\n<h2>Occupational safety and logistics<\/h2>\n<p>Workplaces on the formwork require access, fall protection, and sufficient load-bearing capacity. Crane and lifting points must be defined, and load transports coordinated. When using hydraulic tools, pressure, hose routing, couplings, and emergency stop devices must be checked in advance. Safety requirements and instructions must be adapted to the specific site conditions.<\/p>\n<ul>\n<li>Define exclusion zones for lifting, cutting, and splitting operations with clear signage<\/li>\n<li>Plan hose management and whip-checks for pressurized lines, including periodic leak checks<\/li>\n<li>Coordinate noise and dust control with method selection and pour scheduling<\/li>\n<\/ul>\n<h2>Formwork plan in existing structures, conversion, and deconstruction<\/h2>\n<p>When building within existing structures, temporary shoring, deconstruction formwork, and cut lines are part of the planning. In building gutting and selective deconstruction, concrete and reinforcement are removed in sections to control load redistribution. For openings in load-bearing members, temporary supports are first installed according to the plan; removal then proceeds in small increments. Concrete demolition shears allow precise nibbling along marked cut lines, while hydraulic wedge splitters separate massive zones with low vibration. <a href=\"https:\/\/www.darda.de\/en\/product-overview\/steel-shears\">Steel shears for cutting reinforcement<\/a> can cut reinforcement without the spark generation associated with thermal cutting.<\/p>\n<ul>\n<li>Concrete demolition and special demolition: positionally accurate work with limited access and sensitive neighboring structures<\/li>\n<li>Decoupled hydraulic power packs: energy-efficient tool supply with low emissions<\/li>\n<li>Dust and noise reduction: choice of methods and increment sizes according to the site environment<\/li>\n<\/ul>\n<p>Monitoring of adjacent components is recommended for sensitive work: define trigger levels and implement vibration, crack-width, and settlement checks. Sequencing, shore pre-loading, and back-propping are coordinated to maintain stable load paths during and after removal.<\/p>\n<h2>Formwork planning in tunneling and structural concrete construction<\/h2>\n<p>In rock and tunnel construction, cycles, formwork travelers, inner forms, and pouring windows shape the formwork plan. Joint patterns, anchor zones, and blockouts for embedded items (drainage, cables, ventilation) must be coordinated early. For over- or under-profiles, targeted rock excavation may be required before formwork assembly. In portal and tie-in situations, hydraulic wedge splitters help shape rock edges precisely without endangering surrounding structures through vibrations.<\/p>\n<p>Cycle planning defines section lengths, reinforcement interfaces, curing times, and logistics for advancing formwork. Clearance to rock bolts and temporary linings is verified before each move to prevent clashes.<\/p>\n<h3>Thermal and scheduling boundary conditions<\/h3>\n<p>Temperature, heat of hydration, and member thickness influence fresh concrete pressure, stripping times, and curing. In cold weather, protective measures against cooling must be planned; for large member thicknesses, construction joints and cooling concepts must be considered.<\/p>\n<ul>\n<li>Use maturity methods to forecast early-age strength and optimize stripping times<\/li>\n<li>Plan insulated formwork or active cooling where heat management is critical<\/li>\n<li>Adapt pour sizes and intervals to ambient conditions and logistics capacity<\/li>\n<\/ul>\n<h2>Typical errors in the formwork plan and their correction<\/h2>\n<ul>\n<li>Missing or colliding blockouts: clash detection in planning; if needed on site, precise rework with concrete demolition shears<\/li>\n<li>Insufficient anchor spacing: retrofit anchors and adjust the placing rate<\/li>\n<li>Overlooked load cases (e.g., wind, assembly): strengthen the shoring structure, add bracing<\/li>\n<li>Unfavorable joint layout: correct by changing the sequencing; if necessary, mill or nibble edges and reprofile<\/li>\n<li>Unrealistic placing rates: adjust to permissible formwork pressure, adapt the logistics<\/li>\n<li>Incomplete edge protection details: specify chamfers, arrises, and protection strips to avoid spalling<\/li>\n<li>Unspecified release agent practice: define product class, application method, and intervals to prevent adhesion and staining<\/li>\n<\/ul>\n<h2>Digital planning and BIM-supported formwork plans<\/h2>\n<p>3D models with 4D scheduling enable visual control of sequencing, anchor and joint grids, and clashes. Bills of materials, assembly sequences, and inspection points are derived directly from the model. On site, digital checklists support acceptance. For later conversions, the as-built model provides a reliable basis to plan openings and deconstruction cut lines in a material-conserving manner.<\/p>\n<p>Interoperable model exchange and consistent IDs for panels, anchors, and pours enable tracking from planning to execution. QR-coded components and mobile access to model views improve traceability and reduce errors at interfaces.<\/p>\n<h2>Sustainability and reuse<\/h2>\n<p>Good formwork planning maximizes the reuse cycles of formwork sheathing and formwork scaffold, reduces offcuts, and avoids rework. Low-vibration removal methods-such as controlled splitting and targeted nibbling-reduce noise and dust, protect neighboring buildings, and facilitate clean separation of concrete and steel. This is particularly advantageous in special-use scenarios with sensitive surroundings.<\/p>\n<p>Specifying durable sheathing qualities, repair strategies for panels, and efficient tie layouts supports circular use. Optimized pour sizes and logistics lower idle crane times and energy demand, contributing to resource-efficient execution.<\/p>\n<h2>Terms and distinctions<\/h2>\n<p>The formwork plan describes the auxiliary structure for shaping. The formwork structural analysis provides the verifications for the support scaffold and anchors. The reinforcement plan governs internal reinforcement, and the work schedule organizes dates and resources. In execution, these documents interlock and are consolidated in approval processes-the quality of the formwork plan has a direct impact on construction time, surface appearance, and the extent of subsequent rework.<\/p>\n<p><em>Related terminology:<\/em> formwork plan or shuttering plan denotes the execution drawing set for formwork and falsework, while shop calculations substantiate load paths and permissible pressures during the pour.<\/p>\n<\/div>\n","protected":false},"excerpt":{"rendered":"<p>A formwork plan is the central working basis for concrete placement in building and civil engineering. It translates structural and architectural requirements into an executable solution made of formwork sheathing, formwork scaffold, anchors, props, and work sequences. Precisely planned formwork shortens construction times, secures the required surface quality, and minimizes <a class=\"moretag\" href=\"https:\/\/www.darda.de\/en\/knowledge\/formwork-plan\">read more&#8230;<\/a><\/p>\n","protected":false},"author":9,"featured_media":0,"parent":14846,"menu_order":0,"comment_status":"open","ping_status":"open","template":"tmpl\/template-wissen.php","meta":{"_acf_changed":false,"footnotes":""},"class_list":["post-19712","page","type-page","status-publish","hentry"],"acf":[],"yoast_head":"<!-- This site is optimized with the Yoast SEO plugin v28.8 - https:\/\/yoast.com\/product\/yoast-seo-wordpress\/ -->\n<title>Formwork Plan in Building &amp; Civil Engineering<\/title>\n<meta name=\"description\" content=\"Expert guide to the formwork plan in concrete construction \u2713 loads, pressure, joints, sequencing for safe execution.\" \/>\n<meta name=\"robots\" content=\"index, follow, max-snippet:-1, max-image-preview:large, max-video-preview:-1\" \/>\n<link rel=\"canonical\" href=\"https:\/\/www.darda.de\/en\/knowledge\/formwork-plan\" \/>\n<meta property=\"og:locale\" content=\"en_US\" \/>\n<meta property=\"og:type\" content=\"article\" \/>\n<meta property=\"og:title\" content=\"Formwork Plan in Building &amp; Civil Engineering\" \/>\n<meta property=\"og:description\" content=\"Expert guide to the formwork plan in concrete construction \u2713 loads, pressure, joints, sequencing for safe execution.\" \/>\n<meta property=\"og:url\" content=\"https:\/\/www.darda.de\/en\/knowledge\/formwork-plan\" \/>\n<meta property=\"og:site_name\" content=\"Darda GmbH\" \/>\n<meta property=\"article:publisher\" content=\"https:\/\/www.facebook.com\/DardaDemolition\" \/>\n<meta property=\"article:modified_time\" content=\"2026-05-15T09:34:03+00:00\" \/>\n<meta name=\"twitter:card\" content=\"summary_large_image\" \/>\n<meta name=\"twitter:label1\" content=\"Est. reading time\" \/>\n\t<meta name=\"twitter:data1\" content=\"9 minutes\" \/>\n<script type=\"application\/ld+json\" class=\"yoast-schema-graph\">{\"@context\":\"https:\\\/\\\/schema.org\",\"@graph\":[{\"@type\":\"WebPage\",\"@id\":\"https:\\\/\\\/www.darda.de\\\/en\\\/knowledge\\\/formwork-plan\",\"url\":\"https:\\\/\\\/www.darda.de\\\/en\\\/knowledge\\\/formwork-plan\",\"name\":\"Formwork Plan in Building & Civil Engineering\",\"isPartOf\":{\"@id\":\"https:\\\/\\\/www.darda.de\\\/en#website\"},\"datePublished\":\"2025-12-10T13:18:26+00:00\",\"dateModified\":\"2026-05-15T09:34:03+00:00\",\"description\":\"Expert guide to the formwork plan in concrete construction \u2713 loads, pressure, joints, sequencing for safe execution.\",\"breadcrumb\":{\"@id\":\"https:\\\/\\\/www.darda.de\\\/en\\\/knowledge\\\/formwork-plan#breadcrumb\"},\"inLanguage\":\"en-US\",\"potentialAction\":[{\"@type\":\"ReadAction\",\"target\":[\"https:\\\/\\\/www.darda.de\\\/en\\\/knowledge\\\/formwork-plan\"]}]},{\"@type\":\"BreadcrumbList\",\"@id\":\"https:\\\/\\\/www.darda.de\\\/en\\\/knowledge\\\/formwork-plan#breadcrumb\",\"itemListElement\":[{\"@type\":\"ListItem\",\"position\":1,\"name\":\"Home\",\"item\":\"https:\\\/\\\/www.darda.de\\\/en\"},{\"@type\":\"ListItem\",\"position\":2,\"name\":\"Knowledge\",\"item\":\"https:\\\/\\\/www.darda.de\\\/en\\\/knowledge\"},{\"@type\":\"ListItem\",\"position\":3,\"name\":\"Formwork plan\"}]},{\"@type\":\"WebSite\",\"@id\":\"https:\\\/\\\/www.darda.de\\\/en#website\",\"url\":\"https:\\\/\\\/www.darda.de\\\/en\",\"name\":\"Darda GmbH\",\"description\":\"\",\"publisher\":{\"@id\":\"https:\\\/\\\/www.darda.de\\\/en#organization\"},\"alternateName\":\"Abbruchwerkzeuge\",\"potentialAction\":[{\"@type\":\"SearchAction\",\"target\":{\"@type\":\"EntryPoint\",\"urlTemplate\":\"https:\\\/\\\/www.darda.de\\\/en?s={search_term_string}\"},\"query-input\":{\"@type\":\"PropertyValueSpecification\",\"valueRequired\":true,\"valueName\":\"search_term_string\"}}],\"inLanguage\":\"en-US\"},{\"@type\":\"Organization\",\"@id\":\"https:\\\/\\\/www.darda.de\\\/en#organization\",\"name\":\"Darda GmbH\",\"url\":\"https:\\\/\\\/www.darda.de\\\/en\",\"logo\":{\"@type\":\"ImageObject\",\"inLanguage\":\"en-US\",\"@id\":\"https:\\\/\\\/www.darda.de\\\/en#\\\/schema\\\/logo\\\/image\\\/\",\"url\":\"https:\\\/\\\/www.darda.de\\\/wp-content\\\/uploads\\\/2017\\\/09\\\/android-icon-192x192-1.png\",\"contentUrl\":\"https:\\\/\\\/www.darda.de\\\/wp-content\\\/uploads\\\/2017\\\/09\\\/android-icon-192x192-1.png\",\"width\":192,\"height\":192,\"caption\":\"Darda GmbH\"},\"image\":{\"@id\":\"https:\\\/\\\/www.darda.de\\\/en#\\\/schema\\\/logo\\\/image\\\/\"},\"sameAs\":[\"https:\\\/\\\/www.facebook.com\\\/DardaDemolition\",\"https:\\\/\\\/www.instagram.com\\\/darda_demolition\",\"https:\\\/\\\/www.youtube.com\\\/user\\\/DardaGmbH\",\"https:\\\/\\\/www.xing.com\\\/pages\\\/darda-gmbh\",\"https:\\\/\\\/de.linkedin.com\\\/company\\\/darda-gmbh\"]}]}<\/script>\n<!-- \/ Yoast SEO plugin. -->","yoast_head_json":{"title":"Formwork Plan in Building & Civil Engineering","description":"Expert guide to the formwork plan in concrete construction \u2713 loads, pressure, joints, sequencing for safe execution.","robots":{"index":"index","follow":"follow","max-snippet":"max-snippet:-1","max-image-preview":"max-image-preview:large","max-video-preview":"max-video-preview:-1"},"canonical":"https:\/\/www.darda.de\/en\/knowledge\/formwork-plan","og_locale":"en_US","og_type":"article","og_title":"Formwork Plan in Building & Civil Engineering","og_description":"Expert guide to the formwork plan in concrete construction \u2713 loads, pressure, joints, sequencing for safe execution.","og_url":"https:\/\/www.darda.de\/en\/knowledge\/formwork-plan","og_site_name":"Darda GmbH","article_publisher":"https:\/\/www.facebook.com\/DardaDemolition","article_modified_time":"2026-05-15T09:34:03+00:00","twitter_card":"summary_large_image","twitter_misc":{"Est. reading time":"9 minutes"},"schema":{"@context":"https:\/\/schema.org","@graph":[{"@type":"WebPage","@id":"https:\/\/www.darda.de\/en\/knowledge\/formwork-plan","url":"https:\/\/www.darda.de\/en\/knowledge\/formwork-plan","name":"Formwork Plan in Building & Civil Engineering","isPartOf":{"@id":"https:\/\/www.darda.de\/en#website"},"datePublished":"2025-12-10T13:18:26+00:00","dateModified":"2026-05-15T09:34:03+00:00","description":"Expert guide to the formwork plan in concrete construction \u2713 loads, pressure, joints, sequencing for safe execution.","breadcrumb":{"@id":"https:\/\/www.darda.de\/en\/knowledge\/formwork-plan#breadcrumb"},"inLanguage":"en-US","potentialAction":[{"@type":"ReadAction","target":["https:\/\/www.darda.de\/en\/knowledge\/formwork-plan"]}]},{"@type":"BreadcrumbList","@id":"https:\/\/www.darda.de\/en\/knowledge\/formwork-plan#breadcrumb","itemListElement":[{"@type":"ListItem","position":1,"name":"Home","item":"https:\/\/www.darda.de\/en"},{"@type":"ListItem","position":2,"name":"Knowledge","item":"https:\/\/www.darda.de\/en\/knowledge"},{"@type":"ListItem","position":3,"name":"Formwork plan"}]},{"@type":"WebSite","@id":"https:\/\/www.darda.de\/en#website","url":"https:\/\/www.darda.de\/en","name":"Darda GmbH","description":"","publisher":{"@id":"https:\/\/www.darda.de\/en#organization"},"alternateName":"Abbruchwerkzeuge","potentialAction":[{"@type":"SearchAction","target":{"@type":"EntryPoint","urlTemplate":"https:\/\/www.darda.de\/en?s={search_term_string}"},"query-input":{"@type":"PropertyValueSpecification","valueRequired":true,"valueName":"search_term_string"}}],"inLanguage":"en-US"},{"@type":"Organization","@id":"https:\/\/www.darda.de\/en#organization","name":"Darda GmbH","url":"https:\/\/www.darda.de\/en","logo":{"@type":"ImageObject","inLanguage":"en-US","@id":"https:\/\/www.darda.de\/en#\/schema\/logo\/image\/","url":"https:\/\/www.darda.de\/wp-content\/uploads\/2017\/09\/android-icon-192x192-1.png","contentUrl":"https:\/\/www.darda.de\/wp-content\/uploads\/2017\/09\/android-icon-192x192-1.png","width":192,"height":192,"caption":"Darda GmbH"},"image":{"@id":"https:\/\/www.darda.de\/en#\/schema\/logo\/image\/"},"sameAs":["https:\/\/www.facebook.com\/DardaDemolition","https:\/\/www.instagram.com\/darda_demolition","https:\/\/www.youtube.com\/user\/DardaGmbH","https:\/\/www.xing.com\/pages\/darda-gmbh","https:\/\/de.linkedin.com\/company\/darda-gmbh"]}]}},"_links":{"self":[{"href":"https:\/\/www.darda.de\/en\/wp-json\/wp\/v2\/pages\/19712","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/www.darda.de\/en\/wp-json\/wp\/v2\/pages"}],"about":[{"href":"https:\/\/www.darda.de\/en\/wp-json\/wp\/v2\/types\/page"}],"author":[{"embeddable":true,"href":"https:\/\/www.darda.de\/en\/wp-json\/wp\/v2\/users\/9"}],"replies":[{"embeddable":true,"href":"https:\/\/www.darda.de\/en\/wp-json\/wp\/v2\/comments?post=19712"}],"version-history":[{"count":2,"href":"https:\/\/www.darda.de\/en\/wp-json\/wp\/v2\/pages\/19712\/revisions"}],"predecessor-version":[{"id":27439,"href":"https:\/\/www.darda.de\/en\/wp-json\/wp\/v2\/pages\/19712\/revisions\/27439"}],"up":[{"embeddable":true,"href":"https:\/\/www.darda.de\/en\/wp-json\/wp\/v2\/pages\/14846"}],"wp:attachment":[{"href":"https:\/\/www.darda.de\/en\/wp-json\/wp\/v2\/media?parent=19712"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}