{"id":19508,"date":"2025-11-18T11:41:42","date_gmt":"2025-11-18T10:41:42","guid":{"rendered":"https:\/\/www.darda.de\/?page_id=19508"},"modified":"2026-05-01T08:13:02","modified_gmt":"2026-05-01T06:13:02","slug":"tunnel-face-support","status":"publish","type":"page","link":"https:\/\/www.darda.de\/en\/knowledge\/tunnel-face-support","title":{"rendered":"Tunnel face support"},"content":{"rendered":"<div class=\"wissen-inhaltsbereich\">\n<p>Tunnel face support is a central topic in tunnel construction and underground excavation. It links geotechnical design with practical execution and aims to keep the tunnel face stable, avoid fallouts, and enable controlled advance. In practice, it touches numerous work steps, from injections and shotcrete to reprofiling. Devices from Darda GmbH &#8211; such as <em>hydraulic splitter<\/em> or <em>concrete pulverizer<\/em> &#8211; are used in adjacent work phases, for example for controlled loosening of blockwork at the tunnel face, careful removal of shotcrete layers, or precise adjustment of the excavation profile without vibrations.<\/p>\n<ul>\n<li><strong>Objectives of face support:<\/strong> stabilize the excavation front, control deformation, manage groundwater and pore pressures, and enable a predictable construction sequence with low emissions.<\/li>\n<\/ul>\n<h2>Definition: What is meant by tunnel face support?<\/h2>\n<p>Tunnel face support comprises all temporary and advance measures that ensure the stability of the <strong>tunnel face<\/strong> &#8211; the excavation surface facing the tunnel cross-section. The goal is to support the rock mass or soil near the excavation front, limit deformations, control water inflow, and enable a safe construction sequence. The specific configuration depends on geology, groundwater conditions, the excavation method (e.g., blasting works, partial-face cutting, excavator excavation), as well as on the cross-section and sequence of construction phases. Typical elements are shotcrete, lattice girder beams, face bolts (spiles), pipe umbrellas, injections, and &#8211; in special cases &#8211; ground freezing.<\/p>\n<p>Face support measures are typically <em>temporary and advance<\/em> in nature and interact with the primary lining. Their effectiveness relies on short process chains, early ring closure, and strict sequencing with excavation. In observation-driven approaches, measures are dimensioned conservatively at first and then adapted based on monitoring.<\/p>\n<h2>Background: Geotechnical fundamentals and actions<\/h2>\n<p>The load-bearing behavior at the tunnel face is influenced by in-situ stresses, stand-up time of the material, bedding, jointing, cohesion and friction angle, as well as pore water pressure. Rock strengths, discontinuities (e.g., faults, joint sets), and crack patterns determine whether the tunnel face fails in one or multiple layers. In loose ground, settlements and flowing behavior dominate; in hard rock, wedge- and block-wise fallouts are more common. These differences shape the choice of support measures: In highly jointed rock, advance spiles improve composite action; in softer soils, pipe umbrellas and injections stabilize the face zone; under high water inflow, sealing injections and, if necessary, freezing reduce risk. For locally decoupling blockwork or low-stress profile trimming, Darda GmbH\u2019s <a href=\"https:\/\/www.darda.de\/en\/product-overview\/hydraulic-rock-and-concrete-splitters\">hydraulic rock and concrete splitters<\/a> can be used to avoid vibrations and not impair the stability of the remaining tunnel face.<\/p>\n<ul>\n<li><strong>Typical failure mechanisms:<\/strong> shear cones and face extrusion in soft ground, chimneying in coarse-grained soils, and wedge sliding or buckling along discontinuities in rock.<\/li>\n<li><strong>Key influencing factors:<\/strong> overburden and stress ratio, groundwater level and permeability, face inclination, excavation advance length, and time-dependent degradation of material strength.<\/li>\n<li><strong>Action principles:<\/strong> reduce driving forces (shorter rounds, staged excavation), increase resisting forces (pre-support, reinforcement), and control boundary conditions (sealing, drainage, freezing).<\/li>\n<\/ul>\n<h2>Overview of tunnel face support methods<\/h2>\n<p>The selection of methods is based on ground investigations, prediction models, and a monitoring-led construction sequence. Several methods are often combined to increase the safety of the advance.<\/p>\n<ul>\n<li><strong>Selection criteria:<\/strong> stand-up time and deformability, groundwater conditions, accessibility for drilling and installation, required advance rates, and constraints from ventilation and space.<\/li>\n<\/ul>\n<h3>Shotcrete, lattice girder beams, and rapid ring closure<\/h3>\n<p>Freshly excavated tunnel face surfaces are stabilized by prompt application of shotcrete. Lattice girder beams and reinforcement mesh distribute loads; an advance ring closure reduces deformations. During reprofiling or when exposing measuring points, the gentle removal of shotcrete layers can be carried out with <em>concrete pulverizer<\/em> from Darda GmbH to avoid damaging components or rock surfaces.<\/p>\n<p><strong>Quality notes:<\/strong> verify minimum thickness and rebound, maintain curing and ventilation conditions, and avoid overbreak that would weaken the arch effect.<\/p>\n<h3>Face bolts (spiles) and spile umbrellas<\/h3>\n<p>Face bolts anchor loosened zones in load-bearing rock. Spiles arranged in series form an umbrella that bridges the excavation front. Drilling, installation, grouting, and fixing must be tightly coordinated. When trimming protruding reinforcement or removing local concrete protrusions at connection areas, <em>concrete pulverizer<\/em> delivers precise work.<\/p>\n<p><strong>Execution tips:<\/strong> control drilling deviation, ensure complete grout filling, and stagger lengths to optimize overlap in successive rounds.<\/p>\n<h3>Pipe umbrella (forepoling)<\/h3>\n<p>A pipe umbrella consists of steel pipes installed ahead of the face that cover the tunnel face and reduce settlements. It is particularly suitable in soft formations with groundwater. For precise fitting of cut-in areas or removal of temporary packers or shims, <em>hydraulic splitter<\/em> can be used to remove material in a controlled manner.<\/p>\n<p><strong>Design aspects:<\/strong> define pipe spacing, overlap length, and tip treatment; assess interaction with subsequent excavation stages and expected settlement troughs.<\/p>\n<h3>Injections and sealing<\/h3>\n<p>Grouting with cement or resin systems increases the tightness and strength of the face zone. The materials are placed via drill channels. Local adjustments at drilling start points, opening small windows in shotcrete, or relocating anchor heads can be performed with low vibration using <em>concrete pulverizer<\/em> or small <em>rock wedge splitter<\/em>.<\/p>\n<p><strong>Control items:<\/strong> track pressures and takes, document volumes and mix designs, and verify spread via probe holes or permeability checks.<\/p>\n<h3>Ground freezing and special measures<\/h3>\n<p>Freezing creates temporary load-bearing capacity and tightness. It is used for critical combinations of water, loose material, and low overburden. Where component adjustments are required at entry and exit areas, clean cuts in concrete and steel are necessary; in the context of support works, <em>hydraulic shear<\/em>, <em>Multi Cutters<\/em>, or <em>steel shear<\/em> from Darda GmbH may be used in adjacent steps.<\/p>\n<p><strong>Monitoring:<\/strong> temperature control at the face, verification of frozen wall closure, and staged excavation to maintain thermal balance.<\/p>\n<h2>Interfaces to Darda GmbH equipment<\/h2>\n<p>Tunnel face support itself is a system of geotechnical planning and construction execution. At numerous interfaces, tools from Darda GmbH support safe, precise, and low-vibration implementation.<\/p>\n<ul>\n<li><strong>Hydraulic splitter \/ rock wedge splitter:<\/strong> Local loosening of blockwork at the tunnel face, creating relief cracks, reprofiling excavations without blasting vibrations. Relevant application areas: <em>rock excavation and tunnel construction<\/em>, <em>special demolition<\/em>, <em>natural stone extraction<\/em>.<\/li>\n<li><strong>Concrete pulverizer:<\/strong> Selective removal of shotcrete, exposing survey marks and injection ports, preparing contact faces for lattice girders, removing temporary concreting aids. Relevant application areas: <em>concrete demolition and special demolition<\/em>, <em>strip-out and cutting<\/em>, <em>rock excavation and tunnel construction<\/em>. (See <a href=\"https:\/\/www.darda.de\/en\/product-overview\/concrete-crushers\">Concrete Crushers<\/a>.)<\/li>\n<li><strong>Hydraulic power pack:<\/strong> Power supply for hydraulic attachments in the tunnel, matched to the required working pressure and flow rates in confined spaces.<\/li>\n<li><strong>Hydraulic shear \/ Multi Cutters:<\/strong> Cutting reinforcement mesh, lattice girder beams, and small steel sections following support works; trimming rebar overhangs.<\/li>\n<li><strong>Steel shear:<\/strong> Cutting rolled sections or temporary steel props during conversion phases, cross-section enlargements, or when dismantling provisional supports.<\/li>\n<li><strong>Tank Cutter:<\/strong> In special situations in underground works &#8211; e.g., during dismantling of tanks, pipelines, or installations in existing drifts &#8211; clean opening of thick walls as part of <em>special demolition<\/em> scenarios.<\/li>\n<\/ul>\n<p><strong>Advantages in the tunnel environment:<\/strong> compact equipment dimensions, low vibration levels, and precise material removal reduce collateral impacts on the stabilized face zone.<\/p>\n<h2>Process in tunnel advance: From advance exploration to support<\/h2>\n<p>A structured process increases safety and quality. A cyclical advance with immediate follow-up support is typical. Defined hold points, short feedback loops, and clear responsibilities are central to reliable execution.<\/p>\n<h3>Advance exploration and prediction<\/h3>\n<p>Geological models, probe drilling, seismic methods, and hydrogeological exploration provide the basis. Design assumptions for the tunnel face are derived from this.<\/p>\n<ul>\n<li><strong>Outputs:<\/strong> face stability appraisal, water ingress forecast, and preliminary selection of pre-support measures including contingency options.<\/li>\n<\/ul>\n<h3>Excavation step<\/h3>\n<p>Partial-face or full-face excavation, depending on cross-section. Tool selection depends on the rock mass and specifications. In sensitive areas, <em>hydraulic splitter<\/em> can minimize vibrations.<\/p>\n<p><strong>Good practice:<\/strong> limit round length in weak zones, maintain clean drilling patterns, and prevent overbreak to protect subsequent support.<\/p>\n<h3>Primary support<\/h3>\n<p>Immediately after excavation, shotcrete, anchors, spiles, and, if needed, a pipe umbrella follow. Early ring closure is crucial.<\/p>\n<p><strong>Interfaces:<\/strong> ensure sufficient overlap of pre-support, verify bearing against lattice girders, and maintain access for injections and monitoring points.<\/p>\n<h3>Reprofiling and adjustments<\/h3>\n<p>Protrusions and local irregularities are removed. <em>Concrete pulverizer<\/em> enables controlled corrections on shotcrete and concrete members without weakening adjacent supports.<\/p>\n<p><strong>Tolerances:<\/strong> comply with specified excavation profiles and clearances to safeguard lining thickness and equipment envelopes.<\/p>\n<h3>Control and monitoring<\/h3>\n<p>Survey bolts, convergence measurements, settlement gauges, and water levels serve assessment. The results feed into the adjustment of support parameters.<\/p>\n<ul>\n<li><strong>Trigger levels:<\/strong> green-amber-red criteria for deformations, face conditions, and inflows initiate predefined corrective actions and additional pre-support where required.<\/li>\n<\/ul>\n<h2>Design, quality assurance, and documentation<\/h2>\n<p>Design follows national and European regulations as well as project-specific requirements. The observational method and adaptive design are common: measures are planned, monitored during construction, and adjusted as needed. Complete documentation of drilling logs, injection volumes, anchor pull-out tests, shotcrete classes, and reprofiling is part of quality assurance.<\/p>\n<ul>\n<li><strong>Acceptance checks:<\/strong> shotcrete thickness and strength verification, load tests on anchors and spiles, permeability reduction evidence after injections, and geometric control of the excavation profile.<\/li>\n<li><strong>Process KPIs:<\/strong> advance rate, non-conformance count, water ingress rates, and rework share in reprofiling.<\/li>\n<li><strong>Traceability:<\/strong> batch records for grouts and shotcrete, calibration of gauges and pumps, and photo logs of the face condition before and after support.<\/li>\n<\/ul>\n<h2>Occupational safety, emissions, and construction environment<\/h2>\n<p>Underground work imposes high demands on safety, ventilation, and noise control. Low vibration levels &#8211; for example, hydraulic splitting of rock &#8211; can reduce vibrations, secondary cracking, and emissions. Dust suppression via spray mist, safe handling of high-pressure lines of the <em>hydraulic power pack<\/em>, and clear haul roads are essential points. Notes on legal requirements are project- and country-specific and should always be interpreted in a general and precautionary manner.<\/p>\n<ul>\n<li><strong>Main risks:<\/strong> face instability, pressurized water breakthroughs, falling objects, and pinch points around hydraulic lines.<\/li>\n<li><strong>Controls:<\/strong> exclusion zones at the face, reliable communication, pressure relief procedures, verified emergency drainage, and regular inspection of hoses, couplings, and protective guards.<\/li>\n<\/ul>\n<h2>Typical challenges and practical solutions<\/h2>\n<ul>\n<li><strong>Blocky fallouts:<\/strong> Advance spiles increase composite action; local stress relief with <em>hydraulic splitter<\/em> prevents uncontrolled detachment of individual wedges.<\/li>\n<li><strong>Water inflow at the tunnel face:<\/strong> Sealing injections and temporary collection lines. Openings for injection ports can be produced cleanly with <em>concrete pulverizer<\/em>.<\/li>\n<li><strong>Shotcrete protrusions into the profile:<\/strong> Precise removal without damaging the substrate; the combination of <em>concrete pulverizer<\/em> and controlled splitting enables fine adjustments.<\/li>\n<li><strong>Steel components in the way:<\/strong> Lattice girder beams or provisional steel beams are cut with <em>hydraulic shear<\/em>, <em>Multi Cutters<\/em>, or <em>steel shear<\/em> to avoid hindering subsequent steps.<\/li>\n<li><strong>Running ground or face extrusion:<\/strong> Reduce round length, apply pipe umbrellas and pre-grouting, and adjust excavation sequence to maintain confinement.<\/li>\n<li><strong>Limited stand-up time:<\/strong> Prepare immediate shotcreting, ensure material availability, and use pre-installed survey marks for rapid control.<\/li>\n<\/ul>\n<h2>Application areas and interfaces to advance and deconstruction works<\/h2>\n<p>Tunnel face support appears not only in classical tunnel construction but also in drivages of adits, caverns, cross-passages, shafts, and niches. In <em>natural stone extraction<\/em>, advance supports and targeted splitting help release rock heads in a controlled manner. In <em>concrete demolition and special demolition<\/em> &#8211; for example, when opening existing cross-sections or installing connections &#8211; clean cuts and low-vibration methods are important to avoid impairing the structural stability of adjacent components. For <em>strip-out and cutting<\/em> in existing drifts, concrete pulverizers and shears help remove installations without weakening the primary support. In <em>special demolition<\/em> scenarios, such as beneath sensitive structures or in densely built environments, low vibrations and precise work are crucial.<\/p>\n<ul>\n<li><strong>Interfaces across project phases:<\/strong> preparatory works before the main drive, temporary conversions at cross-passages, and dismantling sequences after completion of primary support.<\/li>\n<\/ul>\n<h2>Logistics, power supply, and maintenance in underground construction<\/h2>\n<p>The spatial constraints in advance areas call for compact, reliable power sources and short setup times. Darda GmbH <a href=\"https:\/\/www.darda.de\/en\/product-overview\/hydraulic-power-units\">compact hydraulic power units<\/a> deliver the required performance for <em>hydraulic splitter<\/em>, <em>concrete pulverizer<\/em>, and shears. Hose routing, couplings, pressure monitoring, and regular leak checks are central maintenance tasks. Careful equipment selection and preventive maintenance contribute to availability and support adherence to the construction schedule.<\/p>\n<ul>\n<li><strong>Best practices:<\/strong> use color-coded hoses and quick couplings, plan spare tool availability, schedule shift-based inspections, and document pressure settings for repeatability.<\/li>\n<li><strong>Environmental aspects:<\/strong> minimize oil losses, handle fluids with spill protection, and keep work areas clean to maintain safe footing around the face.<\/li>\n<\/ul>\n<\/div>\n","protected":false},"excerpt":{"rendered":"<p>Tunnel face support is a central topic in tunnel construction and underground excavation. It links geotechnical design with practical execution and aims to keep the tunnel face stable, avoid fallouts, and enable controlled advance. In practice, it touches numerous work steps, from injections and shotcrete to reprofiling. Devices from Darda <a class=\"moretag\" href=\"https:\/\/www.darda.de\/en\/knowledge\/tunnel-face-support\">read more&#8230;<\/a><\/p>\n","protected":false},"author":9,"featured_media":0,"parent":14846,"menu_order":0,"comment_status":"open","ping_status":"open","template":"tmpl\/template-wissen.php","meta":{"_acf_changed":false,"footnotes":""},"class_list":["post-19508","page","type-page","status-publish","hentry"],"acf":[],"yoast_head":"<!-- This site is optimized with the Yoast SEO plugin v28.8 - https:\/\/yoast.com\/product\/yoast-seo-wordpress\/ -->\n<title>Tunnel Face Support | Tunneling Methods &amp; Safety<\/title>\n<meta name=\"description\" content=\"Safe tunneling with tunnel face support \u2713 Stabilizes the excavation face, limits deformation and controls water inflow.\" \/>\n<meta name=\"robots\" content=\"index, follow, max-snippet:-1, max-image-preview:large, max-video-preview:-1\" \/>\n<link rel=\"canonical\" href=\"https:\/\/www.darda.de\/en\/knowledge\/tunnel-face-support\" \/>\n<meta property=\"og:locale\" content=\"en_US\" \/>\n<meta property=\"og:type\" content=\"article\" \/>\n<meta property=\"og:title\" content=\"Tunnel Face Support | Tunneling Methods &amp; Safety\" \/>\n<meta property=\"og:description\" content=\"Safe tunneling with tunnel face support \u2713 Stabilizes the excavation face, limits deformation and controls water inflow.\" \/>\n<meta property=\"og:url\" content=\"https:\/\/www.darda.de\/en\/knowledge\/tunnel-face-support\" \/>\n<meta property=\"og:site_name\" content=\"Darda GmbH\" \/>\n<meta property=\"article:publisher\" content=\"https:\/\/www.facebook.com\/DardaDemolition\" \/>\n<meta property=\"article:modified_time\" content=\"2026-05-01T06:13:02+00:00\" \/>\n<meta name=\"twitter:card\" content=\"summary_large_image\" \/>\n<meta name=\"twitter:label1\" content=\"Est. reading time\" \/>\n\t<meta name=\"twitter:data1\" content=\"10 minutes\" \/>\n<script type=\"application\/ld+json\" class=\"yoast-schema-graph\">{\"@context\":\"https:\\\/\\\/schema.org\",\"@graph\":[{\"@type\":\"WebPage\",\"@id\":\"https:\\\/\\\/www.darda.de\\\/en\\\/knowledge\\\/tunnel-face-support\",\"url\":\"https:\\\/\\\/www.darda.de\\\/en\\\/knowledge\\\/tunnel-face-support\",\"name\":\"Tunnel Face Support | Tunneling Methods & Safety\",\"isPartOf\":{\"@id\":\"https:\\\/\\\/www.darda.de\\\/en#website\"},\"datePublished\":\"2025-11-18T10:41:42+00:00\",\"dateModified\":\"2026-05-01T06:13:02+00:00\",\"description\":\"Safe tunneling with tunnel face support \u2713 Stabilizes the excavation face, limits deformation and controls water inflow.\",\"breadcrumb\":{\"@id\":\"https:\\\/\\\/www.darda.de\\\/en\\\/knowledge\\\/tunnel-face-support#breadcrumb\"},\"inLanguage\":\"en-US\",\"potentialAction\":[{\"@type\":\"ReadAction\",\"target\":[\"https:\\\/\\\/www.darda.de\\\/en\\\/knowledge\\\/tunnel-face-support\"]}]},{\"@type\":\"BreadcrumbList\",\"@id\":\"https:\\\/\\\/www.darda.de\\\/en\\\/knowledge\\\/tunnel-face-support#breadcrumb\",\"itemListElement\":[{\"@type\":\"ListItem\",\"position\":1,\"name\":\"Home\",\"item\":\"https:\\\/\\\/www.darda.de\\\/en\"},{\"@type\":\"ListItem\",\"position\":2,\"name\":\"Knowledge\",\"item\":\"https:\\\/\\\/www.darda.de\\\/en\\\/knowledge\"},{\"@type\":\"ListItem\",\"position\":3,\"name\":\"Tunnel face support\"}]},{\"@type\":\"WebSite\",\"@id\":\"https:\\\/\\\/www.darda.de\\\/en#website\",\"url\":\"https:\\\/\\\/www.darda.de\\\/en\",\"name\":\"Darda GmbH\",\"description\":\"\",\"publisher\":{\"@id\":\"https:\\\/\\\/www.darda.de\\\/en#organization\"},\"alternateName\":\"Abbruchwerkzeuge\",\"potentialAction\":[{\"@type\":\"SearchAction\",\"target\":{\"@type\":\"EntryPoint\",\"urlTemplate\":\"https:\\\/\\\/www.darda.de\\\/en?s={search_term_string}\"},\"query-input\":{\"@type\":\"PropertyValueSpecification\",\"valueRequired\":true,\"valueName\":\"search_term_string\"}}],\"inLanguage\":\"en-US\"},{\"@type\":\"Organization\",\"@id\":\"https:\\\/\\\/www.darda.de\\\/en#organization\",\"name\":\"Darda GmbH\",\"url\":\"https:\\\/\\\/www.darda.de\\\/en\",\"logo\":{\"@type\":\"ImageObject\",\"inLanguage\":\"en-US\",\"@id\":\"https:\\\/\\\/www.darda.de\\\/en#\\\/schema\\\/logo\\\/image\\\/\",\"url\":\"https:\\\/\\\/www.darda.de\\\/wp-content\\\/uploads\\\/2017\\\/09\\\/android-icon-192x192-1.png\",\"contentUrl\":\"https:\\\/\\\/www.darda.de\\\/wp-content\\\/uploads\\\/2017\\\/09\\\/android-icon-192x192-1.png\",\"width\":192,\"height\":192,\"caption\":\"Darda GmbH\"},\"image\":{\"@id\":\"https:\\\/\\\/www.darda.de\\\/en#\\\/schema\\\/logo\\\/image\\\/\"},\"sameAs\":[\"https:\\\/\\\/www.facebook.com\\\/DardaDemolition\",\"https:\\\/\\\/www.instagram.com\\\/darda_demolition\",\"https:\\\/\\\/www.youtube.com\\\/user\\\/DardaGmbH\",\"https:\\\/\\\/www.xing.com\\\/pages\\\/darda-gmbh\",\"https:\\\/\\\/de.linkedin.com\\\/company\\\/darda-gmbh\"]}]}<\/script>\n<!-- \/ Yoast SEO plugin. -->","yoast_head_json":{"title":"Tunnel Face Support | Tunneling Methods & Safety","description":"Safe tunneling with tunnel face support \u2713 Stabilizes the excavation face, limits deformation and controls water inflow.","robots":{"index":"index","follow":"follow","max-snippet":"max-snippet:-1","max-image-preview":"max-image-preview:large","max-video-preview":"max-video-preview:-1"},"canonical":"https:\/\/www.darda.de\/en\/knowledge\/tunnel-face-support","og_locale":"en_US","og_type":"article","og_title":"Tunnel Face Support | Tunneling Methods & Safety","og_description":"Safe tunneling with tunnel face support \u2713 Stabilizes the excavation face, limits deformation and controls water inflow.","og_url":"https:\/\/www.darda.de\/en\/knowledge\/tunnel-face-support","og_site_name":"Darda GmbH","article_publisher":"https:\/\/www.facebook.com\/DardaDemolition","article_modified_time":"2026-05-01T06:13:02+00:00","twitter_card":"summary_large_image","twitter_misc":{"Est. reading time":"10 minutes"},"schema":{"@context":"https:\/\/schema.org","@graph":[{"@type":"WebPage","@id":"https:\/\/www.darda.de\/en\/knowledge\/tunnel-face-support","url":"https:\/\/www.darda.de\/en\/knowledge\/tunnel-face-support","name":"Tunnel Face Support | Tunneling Methods & Safety","isPartOf":{"@id":"https:\/\/www.darda.de\/en#website"},"datePublished":"2025-11-18T10:41:42+00:00","dateModified":"2026-05-01T06:13:02+00:00","description":"Safe tunneling with tunnel face support \u2713 Stabilizes the excavation face, limits deformation and controls water inflow.","breadcrumb":{"@id":"https:\/\/www.darda.de\/en\/knowledge\/tunnel-face-support#breadcrumb"},"inLanguage":"en-US","potentialAction":[{"@type":"ReadAction","target":["https:\/\/www.darda.de\/en\/knowledge\/tunnel-face-support"]}]},{"@type":"BreadcrumbList","@id":"https:\/\/www.darda.de\/en\/knowledge\/tunnel-face-support#breadcrumb","itemListElement":[{"@type":"ListItem","position":1,"name":"Home","item":"https:\/\/www.darda.de\/en"},{"@type":"ListItem","position":2,"name":"Knowledge","item":"https:\/\/www.darda.de\/en\/knowledge"},{"@type":"ListItem","position":3,"name":"Tunnel face support"}]},{"@type":"WebSite","@id":"https:\/\/www.darda.de\/en#website","url":"https:\/\/www.darda.de\/en","name":"Darda GmbH","description":"","publisher":{"@id":"https:\/\/www.darda.de\/en#organization"},"alternateName":"Abbruchwerkzeuge","potentialAction":[{"@type":"SearchAction","target":{"@type":"EntryPoint","urlTemplate":"https:\/\/www.darda.de\/en?s={search_term_string}"},"query-input":{"@type":"PropertyValueSpecification","valueRequired":true,"valueName":"search_term_string"}}],"inLanguage":"en-US"},{"@type":"Organization","@id":"https:\/\/www.darda.de\/en#organization","name":"Darda GmbH","url":"https:\/\/www.darda.de\/en","logo":{"@type":"ImageObject","inLanguage":"en-US","@id":"https:\/\/www.darda.de\/en#\/schema\/logo\/image\/","url":"https:\/\/www.darda.de\/wp-content\/uploads\/2017\/09\/android-icon-192x192-1.png","contentUrl":"https:\/\/www.darda.de\/wp-content\/uploads\/2017\/09\/android-icon-192x192-1.png","width":192,"height":192,"caption":"Darda GmbH"},"image":{"@id":"https:\/\/www.darda.de\/en#\/schema\/logo\/image\/"},"sameAs":["https:\/\/www.facebook.com\/DardaDemolition","https:\/\/www.instagram.com\/darda_demolition","https:\/\/www.youtube.com\/user\/DardaGmbH","https:\/\/www.xing.com\/pages\/darda-gmbh","https:\/\/de.linkedin.com\/company\/darda-gmbh"]}]}},"_links":{"self":[{"href":"https:\/\/www.darda.de\/en\/wp-json\/wp\/v2\/pages\/19508","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/www.darda.de\/en\/wp-json\/wp\/v2\/pages"}],"about":[{"href":"https:\/\/www.darda.de\/en\/wp-json\/wp\/v2\/types\/page"}],"author":[{"embeddable":true,"href":"https:\/\/www.darda.de\/en\/wp-json\/wp\/v2\/users\/9"}],"replies":[{"embeddable":true,"href":"https:\/\/www.darda.de\/en\/wp-json\/wp\/v2\/comments?post=19508"}],"version-history":[{"count":2,"href":"https:\/\/www.darda.de\/en\/wp-json\/wp\/v2\/pages\/19508\/revisions"}],"predecessor-version":[{"id":26797,"href":"https:\/\/www.darda.de\/en\/wp-json\/wp\/v2\/pages\/19508\/revisions\/26797"}],"up":[{"embeddable":true,"href":"https:\/\/www.darda.de\/en\/wp-json\/wp\/v2\/pages\/14846"}],"wp:attachment":[{"href":"https:\/\/www.darda.de\/en\/wp-json\/wp\/v2\/media?parent=19508"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}